桥梁建设
橋樑建設
교량건설
BRIDGE CONSTRUCTION
2010年
1期
59-62
,共4页
深水基础%围堰%大体积混凝土%桥梁施工
深水基礎%圍堰%大體積混凝土%橋樑施工
심수기출%위언%대체적혼응토%교량시공
deep water foundation%cofferdam%massive concrete%bridge construction
蔡家湾汉江特大桥167号、168号墩的深水基础采用"先平台后围堰"方案施工.先搭设钢栈桥和钻孔平台进行钻孔桩施工,同步进行双壁钢套箱围堰的设计与加工,利用钻孔平台进行围堰的拼装,采用千斤顶起吊系统下放围堰到设计标高后,进行围堰清基、封底、抽水和承台施工.在该方案实施过程中,采取桩基钻孔与围堰拼装、围堰接高与吸泥下沉、围堰下沉与钢护筒内清渣等工序之间平行作业的方式,节省了工期;巧妙地使用千斤顶和分配梁上的2个螺栓,采用千斤顶起吊系统使围堰下放平稳、安全;根据施工水位对围堰封底厚度进行优化以节约成本.
蔡傢灣漢江特大橋167號、168號墩的深水基礎採用"先平檯後圍堰"方案施工.先搭設鋼棧橋和鑽孔平檯進行鑽孔樁施工,同步進行雙壁鋼套箱圍堰的設計與加工,利用鑽孔平檯進行圍堰的拼裝,採用韆斤頂起弔繫統下放圍堰到設計標高後,進行圍堰清基、封底、抽水和承檯施工.在該方案實施過程中,採取樁基鑽孔與圍堰拼裝、圍堰接高與吸泥下沉、圍堰下沉與鋼護筒內清渣等工序之間平行作業的方式,節省瞭工期;巧妙地使用韆斤頂和分配樑上的2箇螺栓,採用韆斤頂起弔繫統使圍堰下放平穩、安全;根據施工水位對圍堰封底厚度進行優化以節約成本.
채가만한강특대교167호、168호돈적심수기출채용"선평태후위언"방안시공.선탑설강잔교화찬공평태진행찬공장시공,동보진행쌍벽강투상위언적설계여가공,이용찬공평태진행위언적병장,채용천근정기조계통하방위언도설계표고후,진행위언청기、봉저、추수화승태시공.재해방안실시과정중,채취장기찬공여위언병장、위언접고여흡니하침、위언하침여강호통내청사등공서지간평행작업적방식,절성료공기;교묘지사용천근정화분배량상적2개라전,채용천근정기조계통사위언하방평은、안전;근거시공수위대위언봉저후도진행우화이절약성본.
The deep water foundations of Piers No.167 and No.168 of Caijiawan Hanjiang River Bridge were constructed by the scheme of"building the platform first and the cofferdam late".The steel trestle was erected and a boring platform was built first to carry out the construction of the bored piles.At the same time,a double-wall steel boxed cofferdam was designed and manufactured.The platform was used to assemble the cofferdam,the cofferdam was then lowered down into river by the jacking-up system.Once the cofferdam was sunk to the designed elevation,the base inside the cofferdam was cleared off,sealed,the water inside was pumped out and finally the construction of the pile cap would proceed.In the implementation of the scheme,the pile foundation hole boring,the cofferdam assembling,height extension,dredging,sinking and mud clearing-off inside the steel casings were operated in a parallel way and the construction time schedule was shortened.The jacks and the two bolts on the distribution beams were ingeniously utilized.The lowering of the cofferdam into the river by the jacking-up system was stable and safe.The thickness of the basing sealing was optimized in accordance with the construction water levels and the construction cost was therefore saved.