预应力钢筋混凝土%连续箱梁%挂篮%施工
預應力鋼觔混凝土%連續箱樑%掛籃%施工
예응력강근혼응토%련속상량%괘람%시공
介绍一种优化的挂篮施工方法,并对该工法优化方面进行较详细的探讨和实施。
介紹一種優化的掛籃施工方法,併對該工法優化方麵進行較詳細的探討和實施。
개소일충우화적괘람시공방법,병대해공법우화방면진행교상세적탐토화실시。
An optimized construction method of prestressed reinforced concrete continuous box girder by using a suspended wagon is introduced. A detailed discussion and implementation are carried out to the optimized parts of the construction method.