2010年
2期
71-73
,共3页
王翥田%叶亮%张新彦%宋美芹
王翥田%葉亮%張新彥%宋美芹
왕저전%협량%장신언%송미근
MBBR工艺%提标改造%悬浮填料
MBBR工藝%提標改造%懸浮填料
MBBR공예%제표개조%현부전료
MBBR process%upgrading and reconstruction%suspended carrier
介绍了MBBR工艺在无锡芦村污水处理厂升级改造中的应用情况.该升级改造工程规模为20×10~4m~3/d.分三期依次改造,主体改造工艺采用A~2/O投加悬浮填料工艺(即MBBR工艺),出水水质稳定达到一级A排放标准.
介紹瞭MBBR工藝在無錫蘆村汙水處理廠升級改造中的應用情況.該升級改造工程規模為20×10~4m~3/d.分三期依次改造,主體改造工藝採用A~2/O投加懸浮填料工藝(即MBBR工藝),齣水水質穩定達到一級A排放標準.
개소료MBBR공예재무석호촌오수처리엄승급개조중적응용정황.해승급개조공정규모위20×10~4m~3/d.분삼기의차개조,주체개조공예채용A~2/O투가현부전료공예(즉MBBR공예),출수수질은정체도일급A배방표준.
The application of MBBR process to upgrading and reconstruction of Wuxi Lucun WWTP is introduced. This upgrading and reconstruction project with a scale of 20 × 10~4 m~3/d is performed in three phases. The main reconstruction process is A~2/O process with suspended carrier ( MBBR process). The effluent quality can reach the first level A criteria of the national discharge standard.