广州大学学报(自然科学版)
廣州大學學報(自然科學版)
엄주대학학보(자연과학판)
JOURNAL OF GUANGZHOU UNIVERSITY(NATURAL SCIENCE EDITION)
2003年
1期
64-69
,共6页
准高速列车%随机振动%横向激振源%钢筋混凝土桥梁
準高速列車%隨機振動%橫嚮激振源%鋼觔混凝土橋樑
준고속열차%수궤진동%횡향격진원%강근혼응토교량
quasi-high-speed train%random vibration%lateral excitation source%reinforced concrete bridge
将列车桥梁系统视为一整体.根据随机振动能量理论,以列车构架人工蛇行波和实测蛇行波为横向激振源,计算了准高速列车以不同的速度通过钢筋混凝土连续梁桥的振动反应.与测试结果比较,本文的计算结果是比较满意的.
將列車橋樑繫統視為一整體.根據隨機振動能量理論,以列車構架人工蛇行波和實測蛇行波為橫嚮激振源,計算瞭準高速列車以不同的速度通過鋼觔混凝土連續樑橋的振動反應.與測試結果比較,本文的計算結果是比較滿意的.
장열차교량계통시위일정체.근거수궤진동능량이론,이열차구가인공사행파화실측사행파위횡향격진원,계산료준고속열차이불동적속도통과강근혼응토련속량교적진동반응.여측시결과비교,본문적계산결과시비교만의적.
The train and bridge are considered as a whole system. According to the random vibration energy theory, by taking the artificial hunting curves and the actual measured hunting curves of the train frame as the transverse excitation source, the vibrating responses are calculated when a quasi-high-speed train runs through the reinforced concrete multi-span box girder at different speed, the results of which are found to be in satisfactory with test data.