价值工程
價值工程
개치공정
VALUE ENGINEERING
2013年
21期
53-54,55
,共3页
挣值法%前锋线法%进度控制%纠偏措施
掙值法%前鋒線法%進度控製%糾偏措施
쟁치법%전봉선법%진도공제%규편조시
earned value measure%vanguard line method%schedule control%corrective measures
挣值法是一种有效的项目进度监控指标和方法。本文采用挣值法和前锋线法对不同节点的进度进行分析,结合工程项目,寻找滞后原因,制定对策进行纠偏,判定是否达到进度要求并佐证纠偏对策的科学性。优秀监理工程师在进度控制过程中要灵活运用挣值法和前锋线法等进行进度分析检查。
掙值法是一種有效的項目進度鑑控指標和方法。本文採用掙值法和前鋒線法對不同節點的進度進行分析,結閤工程項目,尋找滯後原因,製定對策進行糾偏,判定是否達到進度要求併佐證糾偏對策的科學性。優秀鑑理工程師在進度控製過程中要靈活運用掙值法和前鋒線法等進行進度分析檢查。
쟁치법시일충유효적항목진도감공지표화방법。본문채용쟁치법화전봉선법대불동절점적진도진행분석,결합공정항목,심조체후원인,제정대책진행규편,판정시부체도진도요구병좌증규편대책적과학성。우수감리공정사재진도공제과정중요령활운용쟁치법화전봉선법등진행진도분석검사。
The earned value measure is an efficient project progress monitoring indicator and method. In this paper, the progress of the different node is analyzed by the earned value measure and vanguard line method. Combined with engineering project, it looks for lag reasons, formulates measures for rectifying, judges whether it meets the requirements of schedule and proofs the scientificalness of corrective measures. Good supervision engineers should flexibly use earned value measure and vanguard line method to analyze and inspect schedule in the process of schedule control.