隧道%施工%千枚岩%塌方%预防措施
隧道%施工%韆枚巖%塌方%預防措施
수도%시공%천매암%탑방%예방조시
tunnel%construction%phyllite%collapse%preventive measures
通过试验研究了千枚岩的力学性能,结合隧道本身的特殊性,分析了在余震、强降雨等条件下千枚岩隧道施工塌方的原因,进而给出了相应的塌方预防措施,为类似条件下的千枚岩地段施工积累了经验。
通過試驗研究瞭韆枚巖的力學性能,結閤隧道本身的特殊性,分析瞭在餘震、彊降雨等條件下韆枚巖隧道施工塌方的原因,進而給齣瞭相應的塌方預防措施,為類似條件下的韆枚巖地段施工積纍瞭經驗。
통과시험연구료천매암적역학성능,결합수도본신적특수성,분석료재여진、강강우등조건하천매암수도시공탑방적원인,진이급출료상응적탑방예방조시,위유사조건하적천매암지단시공적루료경험。
This article studies the mechanical performance of the phyllite through test. Combining with the specialty of the tunnel itself, it analyzes the causes of phyllite tunnel construction collapse under the condition of aftershoeks and heavy rain, and shows corresponding collapse preventive measures, which has accumulated experience for the phyllite tunnel section construction under the similar condition.