桩式托换%顶升%纠偏
樁式託換%頂升%糾偏
장식탁환%정승%규편
pile underpinning%lifting-up%deviation
针对某项目工程塔楼由于地基土发生不均匀沉降,致使该塔楼整体向北倾斜的现象,采用地基土桩式托换及顶升纠偏的方法对塔楼进行治理后,塔楼与门楼顶张开裂缝完全恢复,倾斜度小于设计规范所规定的偏差,且变形处于稳定状态,施工及顶升期间塔楼未产生新的裂缝,达到了预期的治理效果。
針對某項目工程塔樓由于地基土髮生不均勻沉降,緻使該塔樓整體嚮北傾斜的現象,採用地基土樁式託換及頂升糾偏的方法對塔樓進行治理後,塔樓與門樓頂張開裂縫完全恢複,傾斜度小于設計規範所規定的偏差,且變形處于穩定狀態,施工及頂升期間塔樓未產生新的裂縫,達到瞭預期的治理效果。
침대모항목공정탑루유우지기토발생불균균침강,치사해탑루정체향북경사적현상,채용지기토장식탁환급정승규편적방법대탑루진행치리후,탑루여문루정장개렬봉완전회복,경사도소우설계규범소규정적편차,차변형처우은정상태,시공급정승기간탑루미산생신적렬봉,체도료예기적치리효과。
According to the uneven settlement of the foundation earthwork in the tower of some program causing the deviation of the whole tower toward north, the paper adopts the pile underpinning of the foundation earthwork and lifting-up deviation method, proves the cracks between the tower and gate tower, its inclination is lower than the error of the design regulation, its deformation is in the stable status, and no new crack appears in the tower of its construction and lifting-up process, so it achieves its expected treatment effect.