以“榆林-济南输气管道工程线路八标段冲沟施工”为例,重点介绍了长输管道在黄土塬冲沟地段的穿越施工经验,通过斜井辅助施工,大大降低了难度和成本,从而确保工程质量、缩短工期、降低施工风险,是一种值得推广应用的施工技术。
以“榆林-濟南輸氣管道工程線路八標段遲溝施工”為例,重點介紹瞭長輸管道在黃土塬遲溝地段的穿越施工經驗,通過斜井輔助施工,大大降低瞭難度和成本,從而確保工程質量、縮短工期、降低施工風險,是一種值得推廣應用的施工技術。
이“유림-제남수기관도공정선로팔표단충구시공”위례,중점개소료장수관도재황토원충구지단적천월시공경험,통과사정보조시공,대대강저료난도화성본,종이학보공정질량、축단공기、강저시공풍험,시일충치득추엄응용적시공기술。
Taking the gulch construction at No. 8 standard section on Yulin-Ji' nan natural gas pipeline engineering as the example, it mainly introduces the experience of crossing construction at long-distance pipeline soil gulch section. Through inclined shaft auxiliary construction, it greatly reduces difficult degree and cost. As a result, it guarantees the project quality, shortens construction duration, and reduces construction risks. Therefore,it is kind of construction technology which is worth promoting.