山西建筑
山西建築
산서건축
SHANXI ARCHITECTURE
2012年
3期
196-197
,共2页
大体积承台%混凝土%温度裂缝%温控%施工技术
大體積承檯%混凝土%溫度裂縫%溫控%施工技術
대체적승태%혼응토%온도렬봉%온공%시공기술
large pile cap%concrete%temperature cracks%temperature control%construction technique
详细介绍了客运专线大体积承台高性能混凝土施工中,采取的温控措施及施工方法,通过优化配合比,在大体积承台混凝土内部预埋冷却水管降温、浇筑后在混凝土表面覆盖土工布保温等措施,对控制裂缝起到了很好的效果。
詳細介紹瞭客運專線大體積承檯高性能混凝土施工中,採取的溫控措施及施工方法,通過優化配閤比,在大體積承檯混凝土內部預埋冷卻水管降溫、澆築後在混凝土錶麵覆蓋土工佈保溫等措施,對控製裂縫起到瞭很好的效果。
상세개소료객운전선대체적승태고성능혼응토시공중,채취적온공조시급시공방법,통과우화배합비,재대체적승태혼응토내부예매냉각수관강온、요축후재혼응토표면복개토공포보온등조시,대공제렬봉기도료흔호적효과。
The paper introduces the temperature control measures and construction methods in the large pile cap high-performance concrete construction of the passenger special lines,and adopts some measures by optimizing the proportional ratio,pre-burying the cool water in the internal part of the large pile cap concrete to lower the temperature,and covering the concrete surface with the earthwork cloth for the insulation,so as to have the better effect of controlling the cracks.