工程地质学报
工程地質學報
공정지질학보
2009年
6期
823-828
,共6页
龙游石窟%开裂%监测%分析
龍遊石窟%開裂%鑑測%分析
룡유석굴%개렬%감측%분석
Longyou caverns%Crack%Monitor%Rock pillar%Environment
龙游石窟1-5号洞室群几百年来一直处于水下,1992年首次被抽干水用于开发旅游.由于抽水前后环境的强烈改变,以及洞内干湿交替明显,所以洞室围岩风化和破坏都十分严重.其中,本文所讨论的3号洞第3-2号岩柱就是已发生严重开裂,并亟待加固.为对该岩柱的加固提供科学依据,需准确把握变形破坏发展情况和据此研究它的变形破坏机理.为此,作者采用JSYCB-73系列电感式测缝仪和钢尺等手段对岩柱开裂的宽度和长度进行监测.根据监测所取得的大量数据和地质条件,对该岩柱的开裂机理进行了分析,得出了以下结论:(1)用来加固邻区的混凝土喷层的重力部分转移到该岩柱上,从而增加了荷载;(2)由于洞内渗水严重、干湿交替、温差变化较大等使风化作用加大.结果,导致该岩柱的强度降低.(3)该岩柱强度的降低和所施加荷载的增加等两个因素最终导致了岩柱被压裂.根据上述研究结论,并考虑文物保护和旅游的需要,提出了治水、地表卸荷、岩柱加锚、加箍等加固措施.加固后的监测数据表明,开裂已不再发展,岩柱已处于稳定.
龍遊石窟1-5號洞室群幾百年來一直處于水下,1992年首次被抽榦水用于開髮旅遊.由于抽水前後環境的彊烈改變,以及洞內榦濕交替明顯,所以洞室圍巖風化和破壞都十分嚴重.其中,本文所討論的3號洞第3-2號巖柱就是已髮生嚴重開裂,併亟待加固.為對該巖柱的加固提供科學依據,需準確把握變形破壞髮展情況和據此研究它的變形破壞機理.為此,作者採用JSYCB-73繫列電感式測縫儀和鋼呎等手段對巖柱開裂的寬度和長度進行鑑測.根據鑑測所取得的大量數據和地質條件,對該巖柱的開裂機理進行瞭分析,得齣瞭以下結論:(1)用來加固鄰區的混凝土噴層的重力部分轉移到該巖柱上,從而增加瞭荷載;(2)由于洞內滲水嚴重、榦濕交替、溫差變化較大等使風化作用加大.結果,導緻該巖柱的彊度降低.(3)該巖柱彊度的降低和所施加荷載的增加等兩箇因素最終導緻瞭巖柱被壓裂.根據上述研究結論,併攷慮文物保護和旅遊的需要,提齣瞭治水、地錶卸荷、巖柱加錨、加箍等加固措施.加固後的鑑測數據錶明,開裂已不再髮展,巖柱已處于穩定.
룡유석굴1-5호동실군궤백년래일직처우수하,1992년수차피추간수용우개발여유.유우추수전후배경적강렬개변,이급동내간습교체명현,소이동실위암풍화화파배도십분엄중.기중,본문소토론적3호동제3-2호암주취시이발생엄중개렬,병극대가고.위대해암주적가고제공과학의거,수준학파악변형파배발전정황화거차연구타적변형파배궤리.위차,작자채용JSYCB-73계렬전감식측봉의화강척등수단대암주개렬적관도화장도진행감측.근거감측소취득적대량수거화지질조건,대해암주적개렬궤리진행료분석,득출료이하결론:(1)용래가고린구적혼응토분층적중력부분전이도해암주상,종이증가료하재;(2)유우동내삼수엄중、간습교체、온차변화교대등사풍화작용가대.결과,도치해암주적강도강저.(3)해암주강도적강저화소시가하재적증가등량개인소최종도치료암주피압렬.근거상술연구결론,병고필문물보호화여유적수요,제출료치수、지표사하、암주가묘、가고등가고조시.가고후적감측수거표명,개렬이불재발전,암주이처우은정.
The caverns No. 1 to No. 5 of Longyou cavern group had been fully filled with water for many hundreds years. In 1992, the water was pumped out d for tourism. Because of the dramtic changes of the condition and the alternation bettween drying and wetting, the rock mass weathering and the damages have been substantial. Such as, the rock pillar No. 3-2 of the cavern No. 3 has developed many cracks. This pillar has to be reinforced immediately. To provide the basis for the pillar reinforcement, it is needed to fully understand the situation of the deformation development in the pillar. This paper presents the monitoring results of the widths and the lengths of the cracks with the jointmeters of JSYCB-73 series and steel ruler. On the basic of the data obtained from the monitoring and the geology conditions, this paper further analyzes the causes of the cracking. The following findings are obtained: (1) part of the weights of concrete materials that are used to reinforce the other part of the cavern increased the load on the pillar;(2) the leakage of the cavern, the alternation bettween drying and wetting and the changes of the temperature enlarged the weathering, which reduced the pillar strength;(3) the two above factors made the growth of cracks in the pillar. Based on the findings, taking into account the cultural relics and the tourism, this paper suggests the protection measures. They include the water-control, unloading the load, installing rock bolts and hoops. The monitored data after the pillar reinforcments show that the cracks has stopped developping,and the pillar has been stable.