预应力混凝土管桩%设计%施工%检测
預應力混凝土管樁%設計%施工%檢測
예응력혼응토관장%설계%시공%검측
prestressed concrete pipe pile%design%construction%inspection technique
文章通过中南地区预应力高强混凝土管桩应用实例,文章总结了在复杂地质条件下使用预应力管桩容易出现的具体问题,并对出现的这些问题的成因进行了深入分析,提出了在设计、施工、检测中应该注意的关键事项,为该地区预应力管桩的设计和施工提供了有参考价值的资料.
文章通過中南地區預應力高彊混凝土管樁應用實例,文章總結瞭在複雜地質條件下使用預應力管樁容易齣現的具體問題,併對齣現的這些問題的成因進行瞭深入分析,提齣瞭在設計、施工、檢測中應該註意的關鍵事項,為該地區預應力管樁的設計和施工提供瞭有參攷價值的資料.
문장통과중남지구예응력고강혼응토관장응용실례,문장총결료재복잡지질조건하사용예응력관장용역출현적구체문제,병대출현적저사문제적성인진행료심입분석,제출료재설계、시공、검측중응해주의적관건사항,위해지구예응력관장적설계화시공제공료유삼고개치적자료.
Based on the of prestressed high strength concrete pipe pile in Hunan province, many problems can't be neglected were summarized for Prestressed concrete pipe pile at complex geologic setting. In-depth analysis was processed on the cause of those problems, and the key proceedings must be regarded were advanced for design, construction and inspection technique. Some referenced suggestions were provided for design and construction of prestressed concrete pipe pile in this zone.