水利学报
水利學報
수리학보
2013年
7期
863-872
,共10页
钟登华%常昊天%刘宁%张平
鐘登華%常昊天%劉寧%張平
종등화%상호천%류저%장평
高堆石坝%土石方调配%场内交通仿真%坝面填筑仿真%施工全过程仿真%实时监控%进度控制
高堆石壩%土石方調配%場內交通倣真%壩麵填築倣真%施工全過程倣真%實時鑑控%進度控製
고퇴석패%토석방조배%장내교통방진%패면전축방진%시공전과정방진%실시감공%진도공제
high rock-filled dam%allocation of earth%traffic simulation%simulation of roller compaction construction%simulation for whole construction process%real-time monitoring%progress control
施工仿真技术的研发为高堆石坝建设中工程进度的分析、优化与控制提供了有效途径。本文结合系统仿真技术、数据库技术、可视化技术、系统集成技术和实时监控技术,开展了高堆石坝施工仿真与优化的理论方法与技术研究。在仿真系统构成方面,将高堆石坝施工仿真与优化系统划分为土石方动态平衡与优化调配、施工场内交通仿真、坝面填筑过程精细化仿真、施工全过程仿真、基于实时监控的动态仿真5个功能模块。分析了各模块的功能、相互关系及实现原理。工程应用实例表明,该系统可有效提高高堆石坝施工组织设计的水平和效率,为工程进度的管理与控制提供重要保证。
施工倣真技術的研髮為高堆石壩建設中工程進度的分析、優化與控製提供瞭有效途徑。本文結閤繫統倣真技術、數據庫技術、可視化技術、繫統集成技術和實時鑑控技術,開展瞭高堆石壩施工倣真與優化的理論方法與技術研究。在倣真繫統構成方麵,將高堆石壩施工倣真與優化繫統劃分為土石方動態平衡與優化調配、施工場內交通倣真、壩麵填築過程精細化倣真、施工全過程倣真、基于實時鑑控的動態倣真5箇功能模塊。分析瞭各模塊的功能、相互關繫及實現原理。工程應用實例錶明,該繫統可有效提高高堆石壩施工組織設計的水平和效率,為工程進度的管理與控製提供重要保證。
시공방진기술적연발위고퇴석패건설중공정진도적분석、우화여공제제공료유효도경。본문결합계통방진기술、수거고기술、가시화기술、계통집성기술화실시감공기술,개전료고퇴석패시공방진여우화적이론방법여기술연구。재방진계통구성방면,장고퇴석패시공방진여우화계통화분위토석방동태평형여우화조배、시공장내교통방진、패면전축과정정세화방진、시공전과정방진、기우실시감공적동태방진5개공능모괴。분석료각모괴적공능、상호관계급실현원리。공정응용실례표명,해계통가유효제고고퇴석패시공조직설계적수평화효솔,위공정진도적관리여공제제공중요보증。
Construction simulation has advantages in the analysis, optimization and control of construction progress. Linked to the technology of system simulation, database, visualization, system integration and re-al-time monitoring, the theory and method of high rock-filled dam construction’s simulation and optimiza-tion is carried out. In the composition of the simulation system, the construction simulation and optimiza-tion system of high rock-filled dam is divided into five modules, which are respectively the dynamic bal-ance and optimization allocation of earth module,the traffic simulation of construction module,the fine sim-ulation of roller compaction construction module, the simulation for whole construction process module and the dynamic simulation based on real-time monitoring module. Their functions, interrelation and realization principles are analyzed. System application results show that the level of construction organization design can be improved effectively. The system can provide support for the management and control of construction progress.