湿法脱硫%烟道%膨胀节%破裂
濕法脫硫%煙道%膨脹節%破裂
습법탈류%연도%팽창절%파렬
WFGD%flue%expansion joint%crack
某发电厂2台660 MW机组脱硫装置在投运后8个月内, GGH至吸收塔原烟道发生很大的整体位移,将吸收塔入口处的膨胀节拉裂,导致烟气泄漏。通过对烟道整体结构的分析,提出了相应的改进措施。实际运行情况证明改造合理有效。
某髮電廠2檯660 MW機組脫硫裝置在投運後8箇月內, GGH至吸收塔原煙道髮生很大的整體位移,將吸收塔入口處的膨脹節拉裂,導緻煙氣洩漏。通過對煙道整體結構的分析,提齣瞭相應的改進措施。實際運行情況證明改造閤理有效。
모발전엄2태660 MW궤조탈류장치재투운후8개월내, GGH지흡수탑원연도발생흔대적정체위이,장흡수탑입구처적팽창절랍렬,도치연기설루。통과대연도정체결구적분석,제출료상응적개진조시。실제운행정황증명개조합리유효。
The excessive displacement of the flue between GGH and absorber happened during eight months after FGD operation in 2×660 MW units of a power plant. The cracks appeared on the expansion joint at the absorber inlet that led to gas leakage. The treatment measure is put forward through the analysis of the whole flue structure. The actual operation after improvement indicates that the retrofit is reasonable and effective.