岩石力学与工程学报
巖石力學與工程學報
암석역학여공정학보
CHINESE JOURNAL OF ROCK MECHANICS AND ENGINEERING
2013年
9期
1807-1812
,共6页
王旭%蒋代军%刘德仁%何菲
王旭%蔣代軍%劉德仁%何菲
왕욱%장대군%류덕인%하비
桩基础%低温多年冻土地基%大直径钻孔灌注桩%地温%回冻%竖向承载特性
樁基礎%低溫多年凍土地基%大直徑鑽孔灌註樁%地溫%迴凍%豎嚮承載特性
장기출%저온다년동토지기%대직경찬공관주장%지온%회동%수향승재특성
pile foundations%low-temperature permafrost ground%large-diameter cast-in-place bored pile%ground temperature%refreezing%vertical bearing behavior
多年冻土地基由于大直径钻孔灌注桩桩身混凝土水化热造成桩周冻土融化,而桩体混凝土灌注初期桩土体系不具备冻结强度,导致钻孔灌注桩初期承载力很低。研究低温多年冻土地基大直径钻孔灌注桩未回冻状态的承载力和变形性质,可为工程施工工期安排提供技术依据。结合青藏铁路索南达杰特大桥工程进行低温多年冻土大直径钻孔灌注桩地温测试及现场静载试验,为此设置桩土界面测温孔(SB)、桩侧测温孔(SC,距离桩壁30 cm)以及未受施工扰动的基准地温孔(JZ)。获得夏季灌注桩混凝土入模温度为11℃,不同龄期桩土体系的地温分布,并分析桩土体系的回冻过程。测试数据表明:混凝土灌注完成30d以后,桩顶至地表下2m为正温,地表下2m到桩底桩身表面均为负温,在-0.43℃~-1.26℃范围内变化;灌注50 d以后,桩土界面地温逐渐降低,为-1.0℃~-1.85℃,与未受扰动天然地基地温相比,桩土体系尚未完全回冻。同时进行不同地温条件下基桩的现场静载试验,分析竖向承载力、变形及桩侧摩阻(或冻结力)分布特性。当加载到最大荷载(7600 kN)时,桩顶竖向位移达到4.93 mm,卸载后未恢复的变形为1.01 mm,说明低温多年冻土地基钻孔灌注桩在未完全回冻状态下(试桩龄期30 d)基桩具有较高竖向承载力,且变形量小。
多年凍土地基由于大直徑鑽孔灌註樁樁身混凝土水化熱造成樁週凍土融化,而樁體混凝土灌註初期樁土體繫不具備凍結彊度,導緻鑽孔灌註樁初期承載力很低。研究低溫多年凍土地基大直徑鑽孔灌註樁未迴凍狀態的承載力和變形性質,可為工程施工工期安排提供技術依據。結閤青藏鐵路索南達傑特大橋工程進行低溫多年凍土大直徑鑽孔灌註樁地溫測試及現場靜載試驗,為此設置樁土界麵測溫孔(SB)、樁側測溫孔(SC,距離樁壁30 cm)以及未受施工擾動的基準地溫孔(JZ)。穫得夏季灌註樁混凝土入模溫度為11℃,不同齡期樁土體繫的地溫分佈,併分析樁土體繫的迴凍過程。測試數據錶明:混凝土灌註完成30d以後,樁頂至地錶下2m為正溫,地錶下2m到樁底樁身錶麵均為負溫,在-0.43℃~-1.26℃範圍內變化;灌註50 d以後,樁土界麵地溫逐漸降低,為-1.0℃~-1.85℃,與未受擾動天然地基地溫相比,樁土體繫尚未完全迴凍。同時進行不同地溫條件下基樁的現場靜載試驗,分析豎嚮承載力、變形及樁側摩阻(或凍結力)分佈特性。噹加載到最大荷載(7600 kN)時,樁頂豎嚮位移達到4.93 mm,卸載後未恢複的變形為1.01 mm,說明低溫多年凍土地基鑽孔灌註樁在未完全迴凍狀態下(試樁齡期30 d)基樁具有較高豎嚮承載力,且變形量小。
다년동토지기유우대직경찬공관주장장신혼응토수화열조성장주동토융화,이장체혼응토관주초기장토체계불구비동결강도,도치찬공관주장초기승재력흔저。연구저온다년동토지기대직경찬공관주장미회동상태적승재력화변형성질,가위공정시공공기안배제공기술의거。결합청장철로색남체걸특대교공정진행저온다년동토대직경찬공관주장지온측시급현장정재시험,위차설치장토계면측온공(SB)、장측측온공(SC,거리장벽30 cm)이급미수시공우동적기준지온공(JZ)。획득하계관주장혼응토입모온도위11℃,불동령기장토체계적지온분포,병분석장토체계적회동과정。측시수거표명:혼응토관주완성30d이후,장정지지표하2m위정온,지표하2m도장저장신표면균위부온,재-0.43℃~-1.26℃범위내변화;관주50 d이후,장토계면지온축점강저,위-1.0℃~-1.85℃,여미수우동천연지기지온상비,장토체계상미완전회동。동시진행불동지온조건하기장적현장정재시험,분석수향승재력、변형급장측마조(혹동결력)분포특성。당가재도최대하재(7600 kN)시,장정수향위이체도4.93 mm,사재후미회복적변형위1.01 mm,설명저온다년동토지기찬공관주장재미완전회동상태하(시장령기30 d)기장구유교고수향승재력,차변형량소。
by construction,denoted by SB,SC,and JZ,respectively,were set up to obtain the corresponding temperatures. The temperature distributions for the pile-soil system at various ages were obtained when the piles were cast in summer and the initial concrete temperature was 11℃. The refreezing process of the pile-soil system as well as the distribution characteristics of the vertical bearing capacity,vertical deformation and skin friction(or freezing force) of the pile under various ground temperatures were analyzed. Test results show that 30 days after the construction of the pile,the temperature along the pile skin is negative(approximately -0.43 ℃--1.26 ℃) except in the section 0-2 m below the ground surface;50 days after the construction of the pile,it becomes a bit lower(approximately-1.0℃--1.85 ℃. C)ompared with the original undisturbed state,the pile-soil system is not fully refrozen. When a maximum vertical load of 7 600 kN is applied,the vertical pile-head displacement is 4.93 mm while the residual deformation after unloading is 1.01 mm. It shows that the pile has a high vertical bearing capacity and a small deformation under a non-fully refreezing condition with the pile age of 30 days.