西北水电
西北水電
서북수전
NORTHWEST WATER POWER
2014年
2期
31-33
,共3页
“5 .12”地震%工程除险%麒麟寺水电站
“5 .12”地震%工程除險%麒麟寺水電站
“5 .12”지진%공정제험%기린사수전참
earthquake happed on May 12,2008%hazard elimination by engineering measures%Qilingsi Hydropower Station
针对麒麟寺水电站工程在汶川“5.12”地震后出现的问题进行了分析总结,提出了相应的解决措施和方案。结合工程实际计算分析了方案的可行性、安全性。
針對麒麟寺水電站工程在汶川“5.12”地震後齣現的問題進行瞭分析總結,提齣瞭相應的解決措施和方案。結閤工程實際計算分析瞭方案的可行性、安全性。
침대기린사수전참공정재문천“5.12”지진후출현적문제진행료분석총결,제출료상응적해결조시화방안。결합공정실제계산분석료방안적가행성、안전성。
Issues, occurred after the earthquake happened o May 12, 2008, on Qilingsi Hydropower Station are analyzed and summa-rized.Corresponding handling measures and schemes are raised.In combination with the actual works, feasibility and safety of these schemes are calculated and studied.