岩石力学与工程学报
巖石力學與工程學報
암석역학여공정학보
CHINESE JOURNAL OF ROCK MECHANICS AND ENGINEERING
2013年
z2期
3619-3626
,共8页
季昌%周顺华%许恺%李晓龙
季昌%週順華%許愷%李曉龍
계창%주순화%허개%리효룡
隧道工程%管片上浮%盾构施工参数%浆液配比%现场试验%抗浮措施
隧道工程%管片上浮%盾構施工參數%漿液配比%現場試驗%抗浮措施
수도공정%관편상부%순구시공삼수%장액배비%현장시험%항부조시
tunnelling engineering%segments upward moving%shield construction parameter%grout proportion%field test%anti-uplift measures
针对盾构掘进施工时常面临的管片局部或整体性上浮问题,依托宁波地区2例施工期发生较大上浮的地铁盾构隧道工程实例,选择地层特性、埋深等外部条件相似的区段建立掘进速度、总推力反力的竖向分力、同步注浆压力等盾构施工参数以及同步注浆浆液配比的现场试验段,并结合试验段管片上浮的现场监测数据分析上述不同单一因素对施工期管片上浮的影响规律。研究结果表明:管片下半侧注浆压力高于上半侧注浆压力时,管片上浮量增大,当压力差达0.3 MPa时,管片上浮量增加约20 mm;总推力反力变化不大的基础上,其竖直向上的分力增大时,管片上浮量相应增大,当分力增加260 kN,管片上浮量增加约15 mm;在同步注浆胶凝材料总量不变、且非胶凝材料掺量不变的基础上,随着粉灰比、水灰比的减小,浆液抗压强度、黏聚力提高,初凝时间缩短,管片上浮量减小,当每3 m3浆液中水泥的相对掺量增加100 kg,管片上浮能减小19.8 mm;掘进速度单因素对施工期管片上浮无明显影响。
針對盾構掘進施工時常麵臨的管片跼部或整體性上浮問題,依託寧波地區2例施工期髮生較大上浮的地鐵盾構隧道工程實例,選擇地層特性、埋深等外部條件相似的區段建立掘進速度、總推力反力的豎嚮分力、同步註漿壓力等盾構施工參數以及同步註漿漿液配比的現場試驗段,併結閤試驗段管片上浮的現場鑑測數據分析上述不同單一因素對施工期管片上浮的影響規律。研究結果錶明:管片下半側註漿壓力高于上半側註漿壓力時,管片上浮量增大,噹壓力差達0.3 MPa時,管片上浮量增加約20 mm;總推力反力變化不大的基礎上,其豎直嚮上的分力增大時,管片上浮量相應增大,噹分力增加260 kN,管片上浮量增加約15 mm;在同步註漿膠凝材料總量不變、且非膠凝材料摻量不變的基礎上,隨著粉灰比、水灰比的減小,漿液抗壓彊度、黏聚力提高,初凝時間縮短,管片上浮量減小,噹每3 m3漿液中水泥的相對摻量增加100 kg,管片上浮能減小19.8 mm;掘進速度單因素對施工期管片上浮無明顯影響。
침대순구굴진시공시상면림적관편국부혹정체성상부문제,의탁저파지구2례시공기발생교대상부적지철순구수도공정실례,선택지층특성、매심등외부조건상사적구단건립굴진속도、총추력반력적수향분력、동보주장압력등순구시공삼수이급동보주장장액배비적현장시험단,병결합시험단관편상부적현장감측수거분석상술불동단일인소대시공기관편상부적영향규률。연구결과표명:관편하반측주장압력고우상반측주장압력시,관편상부량증대,당압력차체0.3 MPa시,관편상부량증가약20 mm;총추력반력변화불대적기출상,기수직향상적분력증대시,관편상부량상응증대,당분력증가260 kN,관편상부량증가약15 mm;재동보주장효응재료총량불변、차비효응재료참량불변적기출상,수착분회비、수회비적감소,장액항압강도、점취력제고,초응시간축단,관편상부량감소,당매3 m3장액중수니적상대참량증가100 kg,관편상부능감소19.8 mm;굴진속도단인소대시공기관편상부무명현영향。
Aiming at the problem of partially or integrally upward moving of tunnel segments during shield tunnel construction,based on the two metro shield tunnel project cases in which the great upward moving occurs in Ningbo, the field test of shield construction parameters,such as tunneling speed,vertical component force of reaction force of total thrust,synchronized grouting pressure and grout proportion,is conducted in the section that the external conditions(formation characteristic and burial depth) are similar. And combined with the monitoring data in the test section,the influence law of aforementioned single factor on segments upward moving during construction is analyzed. The results show that the amount of segment upward moving increases,when the grouting pressure of the lower segment is higher than that of the upper part. When the pressure difference is up to 0.3 MPa,the amount of upward moving increases about 20 mm. On the basis of little change of reaction force of the total thrust,when its vertical component force increases,the amount of upward moving raises correspondingly. When the component force increases by 260 kN,the amount of segment upward moving grows greater to about 15 mm. Keeping the same amount of cementitious material and mixing in equivalent non-cementitious material during synchronized grouting,the compression strength and cohesion of grout improve,the initial setting time shortens and the segment moves less higher with the reduction of ash cement ratio and water cement ratio. When the relative addition of cement in every 3 m3 of grout increases by 100 kg,the amount of segment upward moving decreases by 19.8 mm. the tunnelling speed,alone,has no distinct impact on upward moving of segments during construction.