太平煤矿九采区泵房和变电所位于-320m水平,为开采九采区16上、17煤层服务。针对原支护存在的主要问题,重新进行了维修加固方案设计。
太平煤礦九採區泵房和變電所位于-320m水平,為開採九採區16上、17煤層服務。針對原支護存在的主要問題,重新進行瞭維脩加固方案設計。
태평매광구채구빙방화변전소위우-320m수평,위개채구채구16상、17매층복무。침대원지호존재적주요문제,중신진행료유수가고방안설계。
The pumping station and substation of nine mining area in Taiping Coal is located in the-320m level, serves for mining 16, 17 coal seam in nine mining area. According to the main problems existing in the original supporting scheme, design new reinforcement and repair scheme.