电力建设
電力建設
전력건설
ELECTRIC POWER CONSTRUCTION
2014年
8期
62-66
,共5页
货运索道%承载索%悬链线%计算模型
貨運索道%承載索%懸鏈線%計算模型
화운색도%승재색%현련선%계산모형
cargo cableway%load cable%catenary%computation model
架空输电线路施工专用货运索道多用于高山大岭、地形起伏较大的地区,因此索道架设时承载索的断面参数和张力复杂多变。计算索道承载索荷载后断面参数及张力的变化,该结果对提高货运索道的安全性和经济性具有重要意义。当承载索的跨距足够大时,将连续索道的承载索简化为多跨的悬链线方程组,并假定各索道支架处承载索支点摩阻系数为0,利用Excel的规划求解工具,将各跨水平张力和荷载点高程设置为可变单元格,以各跨支点处张力平衡、空载和荷载时线长平衡及荷载点处荷重与承载索张力的垂直分量平衡为约束条件,快速求解各未知量,从而得出索道承载索断面参数及张力的变化。该模型的计算结果与实测记录相吻合,适用于施工现场的实际应用。
架空輸電線路施工專用貨運索道多用于高山大嶺、地形起伏較大的地區,因此索道架設時承載索的斷麵參數和張力複雜多變。計算索道承載索荷載後斷麵參數及張力的變化,該結果對提高貨運索道的安全性和經濟性具有重要意義。噹承載索的跨距足夠大時,將連續索道的承載索簡化為多跨的懸鏈線方程組,併假定各索道支架處承載索支點摩阻繫數為0,利用Excel的規劃求解工具,將各跨水平張力和荷載點高程設置為可變單元格,以各跨支點處張力平衡、空載和荷載時線長平衡及荷載點處荷重與承載索張力的垂直分量平衡為約束條件,快速求解各未知量,從而得齣索道承載索斷麵參數及張力的變化。該模型的計算結果與實測記錄相吻閤,適用于施工現場的實際應用。
가공수전선로시공전용화운색도다용우고산대령、지형기복교대적지구,인차색도가설시승재색적단면삼수화장력복잡다변。계산색도승재색하재후단면삼수급장력적변화,해결과대제고화운색도적안전성화경제성구유중요의의。당승재색적과거족구대시,장련속색도적승재색간화위다과적현련선방정조,병가정각색도지가처승재색지점마조계수위0,이용Excel적규화구해공구,장각과수평장력화하재점고정설치위가변단원격,이각과지점처장력평형、공재화하재시선장평형급하재점처하중여승재색장력적수직분량평형위약속조건,쾌속구해각미지량,종이득출색도승재색단면삼수급장력적변화。해모형적계산결과여실측기록상문합,괄용우시공현장적실제응용。
The cargo cableway for overhead transmission line is usually used in high mountains and region with great topographic relief.So the parameters and tensions of load cable sections are usually quite complicated and changeable during the installation of cargo cableway.The calculation of the parameters and tensions of load cable with load has important significance to the improvement of the safety and economy of cargo cableway.When the span of the load cable was large enough,the continuous load cable could be simplified to multi-span catenary equations set,and the fulcrum friction coefficient of load cable of cargo cableway could be assumed as zero.Then the level tensions and loading point elevations in every span was set as adjustable cells with using the Programming Function of Microsoft Excel.Based on the constraint conditions:tension-balance in each span fulcrum,line length balance with load and non-load,balance between vertical component of bearing cable tension and total load in loading point,the changes of the parameters and tensions of load cable sections were calculated rapidly.The model,whose calculation results are identical with the actual measured data,can be applied for practical constructions.