介绍了积石峡水电站引水进水口变形监测设计、重点监测仪器原理与计算方法;综合多种监测仪器观测成果对进水口变形规律进行分析与总结,对同类工程的设计与监测方法的改进提供参考。
介紹瞭積石峽水電站引水進水口變形鑑測設計、重點鑑測儀器原理與計算方法;綜閤多種鑑測儀器觀測成果對進水口變形規律進行分析與總結,對同類工程的設計與鑑測方法的改進提供參攷。
개소료적석협수전참인수진수구변형감측설계、중점감측의기원리여계산방법;종합다충감측의기관측성과대진수구변형규률진행분석여총결,대동류공정적설계여감측방법적개진제공삼고。
Design of deformation monitoring, principles of key monitoring instruments and deformationcalculation methodsfor the power intake, Jishixia HydropowerProject , are describedin the paper .In combinationwith the monitoring observationsby instruments , the de-formationlaw of the power intake is analyzed and summarized, which provides reference to similar project for improvement of design and monitoring methods.