以贵州开阳化工有限公司50万t/a合成氨项目11 km输氨管线为例,简述了液氨输送管线的设备布置方案和管道试压要求;介绍了液氨管线的清管方式和注意事项。
以貴州開暘化工有限公司50萬t/a閤成氨項目11 km輸氨管線為例,簡述瞭液氨輸送管線的設備佈置方案和管道試壓要求;介紹瞭液氨管線的清管方式和註意事項。
이귀주개양화공유한공사50만t/a합성안항목11 km수안관선위례,간술료액안수송관선적설비포치방안화관도시압요구;개소료액안관선적청관방식화주의사항。
Taking the ammonia transmission pipeline with 11 km length in ammonia synthesis project with a capacity of 500 000 t/a in Guizhou Kaiy-ang Chemical Engineering Company Ltd.as an example, author has briefly described equipment arrangement scheme of liquid ammonia transmission pipe-line and hydraulic test requirement of pipeline; has introduced the pipeline cleaning mode for pipeline of liquid ammonia and its matters to be noticed .