依据欧洲规范 EC2关于混凝土弹性模型、收缩、徐变随时间变化规定,考虑施工顺序加载、竖向构件压应力差异、伸臂桁架后连接、下料长度调整等因素,结合某超高层建筑结构,实现了施工全过程模拟,获得各施工阶段外框架柱和核心筒剪力墙的竖向变形量及差异,对施工过程中关键构件的承载力进行验算,同时比较了后连接方案对水平伸臂桁架内力的影响。分析结果表明:在超高层设计时必须考虑混凝土收缩徐变等非荷载作用下的变形,竖向构件应考虑竖向变形而产生的压缩量进行预调整,采用后连接的施工措施可以减小水平伸臂桁架的内力。
依據歐洲規範 EC2關于混凝土彈性模型、收縮、徐變隨時間變化規定,攷慮施工順序加載、豎嚮構件壓應力差異、伸臂桁架後連接、下料長度調整等因素,結閤某超高層建築結構,實現瞭施工全過程模擬,穫得各施工階段外框架柱和覈心筒剪力牆的豎嚮變形量及差異,對施工過程中關鍵構件的承載力進行驗算,同時比較瞭後連接方案對水平伸臂桁架內力的影響。分析結果錶明:在超高層設計時必鬚攷慮混凝土收縮徐變等非荷載作用下的變形,豎嚮構件應攷慮豎嚮變形而產生的壓縮量進行預調整,採用後連接的施工措施可以減小水平伸臂桁架的內力。
의거구주규범 EC2관우혼응토탄성모형、수축、서변수시간변화규정,고필시공순서가재、수향구건압응력차이、신비항가후련접、하료장도조정등인소,결합모초고층건축결구,실현료시공전과정모의,획득각시공계단외광가주화핵심통전력장적수향변형량급차이,대시공과정중관건구건적승재력진행험산,동시비교료후련접방안대수평신비항가내력적영향。분석결과표명:재초고층설계시필수고필혼응토수축서변등비하재작용하적변형,수향구건응고필수향변형이산생적압축량진행예조정,채용후련접적시공조시가이감소수평신비항가적내력。
According to European code EC2 about concrete elastic model,shrinkage and creep change over time and considering the construction order of loads,the difference of the vertical compressive stress compo-nents,cantilever truss connections and blanking length adjustment,The paper realized the whole construction process simulation in combination with a super-high building structure and obtained the results of the total ver-tical deformation and the relative deformation between the outer frame and the core-wall.At the same time,it calculated the bearing capacity of key components in every construction stages and compared the internal forces of the horizontal cantilever truss considering connection after construction.Analysis results show that concrete shrinkage and creep deformation must be considered for the design of high-rise building structure,the deforma-tion of the vertical component of vertical deformation should be considered to adjust,and the internal force of horizontal cantilever truss could be reduced through connection after construction.