跨径布置%边中跨比%锚跨%连续箱梁
跨徑佈置%邊中跨比%錨跨%連續箱樑
과경포치%변중과비%묘과%련속상량
span layout%ratio optimization between side span and mid span%anchor span%continuous box girder
对几种跨径布置形式的大跨径混凝土变截面连续箱梁在结构造价,施工风险,结构受力和施工精度等方面进行了论述,提出了在某些特殊地形下,采用边跨比小的连续梁桥可以比常规边跨比的连续梁更优的观点,为今后该类型桥梁的设计提供了一定指导。
對幾種跨徑佈置形式的大跨徑混凝土變截麵連續箱樑在結構造價,施工風險,結構受力和施工精度等方麵進行瞭論述,提齣瞭在某些特殊地形下,採用邊跨比小的連續樑橋可以比常規邊跨比的連續樑更優的觀點,為今後該類型橋樑的設計提供瞭一定指導。
대궤충과경포치형식적대과경혼응토변절면련속상량재결구조개,시공풍험,결구수력화시공정도등방면진행료논술,제출료재모사특수지형하,채용변과비소적련속량교가이비상규변과비적련속량경우적관점,위금후해류형교량적설계제공료일정지도。
This paper discussed large span concrete reduce section continuous box girder of several span layout forms in structural cost, construc- tion risk, structure stress, construction accuracy and other aspects. Put forward the view that in some special terrain, using continuous box girder with small side span was batter than continuous box girder with conventional side span. Provide certain guidance to this type of bridge design.