铁道建筑技术
鐵道建築技術
철도건축기술
RAILWAY CONSTRUCTION TECHNOLOGY
2012年
10期
60-61,65
,共3页
高铁%风屏障%基础施工%植筋
高鐵%風屏障%基礎施工%植觔
고철%풍병장%기출시공%식근
high speed railway%wind barrier%foundation construction%bonded rebar
结合京沪高铁工程实例,详细阐述了风屏障基础施工的底面及侧面凿毛、打眼(竖向钻眼与水平钻眼)、清孔、注胶植筋、钢筋绑扎、模板支立、混凝土浇筑、养护等施工工艺及质量控制,可为类似工程提供借鉴。
結閤京滬高鐵工程實例,詳細闡述瞭風屏障基礎施工的底麵及側麵鑿毛、打眼(豎嚮鑽眼與水平鑽眼)、清孔、註膠植觔、鋼觔綁扎、模闆支立、混凝土澆築、養護等施工工藝及質量控製,可為類似工程提供藉鑒。
결합경호고철공정실례,상세천술료풍병장기출시공적저면급측면착모、타안(수향찬안여수평찬안)、청공、주효식근、강근방찰、모판지립、혼응토요축、양호등시공공예급질량공제,가위유사공정제공차감。
Combined wind barrier construction of the Beijing-Shanghai high-speed rail technology,the paper introduces the process and quality control technologies concerning wind barrier: the bottom and side chiseling,drilling(vertical drilling and horizontal drilling),reinforced eye Khong,plastic injection anchorage regulatory requirements,wind barrier bolt anchorage steps,steel banding,the template support legislation reinforcement,concreting,maintenance and construction process,which provides reference for similar projects.