山西建筑
山西建築
산서건축
SHANXI ARCHITECTURE
2012年
19期
90-91
,共2页
边坡%稳定性评价%锚喷%锚杆格构
邊坡%穩定性評價%錨噴%錨桿格構
변파%은정성평개%묘분%묘간격구
slope%stability evaluation%boh-shotcrete%anchor lattice
结合梧州市第二污水处理厂场地开挖形成的边坡,对该边坡进行稳定性评价,确定运用锚喷+锚杆格构的边坡治理方案,阐述了该方案的工艺流程及技术要求,边坡监测结果表明治理效果良好。
結閤梧州市第二汙水處理廠場地開挖形成的邊坡,對該邊坡進行穩定性評價,確定運用錨噴+錨桿格構的邊坡治理方案,闡述瞭該方案的工藝流程及技術要求,邊坡鑑測結果錶明治理效果良好。
결합오주시제이오수처리엄장지개알형성적변파,대해변파진행은정성평개,학정운용묘분+묘간격구적변파치리방안,천술료해방안적공예류정급기술요구,변파감측결과표명치리효과량호。
Combining with the slope formed by the excavation at the site of the No. 2 Sewage Treatment Plant at Wuzhou, the study undertakes the stability evaluation of the slope, identifies the slope treatment scheme by adopting the boh-shotcrete + anchor lattice, illustrates the craft procedure and the technical requirements of the scheme, and the results of the slope inspection shows its treatment is better.