电力需求侧管理
電力需求側管理
전력수구측관리
POWER DEMAND SIDE MANAGEMENT
2014年
1期
40-43
,共4页
唐士芳%张志鹏%马宏权%张苇苇
唐士芳%張誌鵬%馬宏權%張葦葦
당사방%장지붕%마굉권%장위위
区域型冷热电三联供%空调负荷%移峰填谷
區域型冷熱電三聯供%空調負荷%移峰填穀
구역형랭열전삼련공%공조부하%이봉전곡
district combined cooling heating and power sys-tem%power load%peak load shifting%post-expodevelopment
对电力负荷现状进行调研,分析了区域型三联供系统的系统特点及其对电网移峰填谷的作用,以世博再开发A片区三联供系统为例,对其各环节对电网移峰填谷的贡献进行了分析。区域型冷热电三联供系统可有效降低空调电力负荷需求,缩小电力负荷的峰谷差值,对我国电网安全运行有着重要的意义。
對電力負荷現狀進行調研,分析瞭區域型三聯供繫統的繫統特點及其對電網移峰填穀的作用,以世博再開髮A片區三聯供繫統為例,對其各環節對電網移峰填穀的貢獻進行瞭分析。區域型冷熱電三聯供繫統可有效降低空調電力負荷需求,縮小電力負荷的峰穀差值,對我國電網安全運行有著重要的意義。
대전력부하현상진행조연,분석료구역형삼련공계통적계통특점급기대전망이봉전곡적작용,이세박재개발A편구삼련공계통위례,대기각배절대전망이봉전곡적공헌진행료분석。구역형랭열전삼련공계통가유효강저공조전력부하수구,축소전력부하적봉곡차치,대아국전망안전운행유착중요적의의。
In this paper, the current power load situation was summarized, and the characteristics of CCHP technology including its peak load shifting function to grid were analyzed.A district CCHP system was introduced, which applied to the post-expo re-gion A.Itsgrid peak-load shifting contributions were researched in different air conditioning system types. CCHP has a very important significanceon reducing the power load for air-conditioning, grid peak-load shifting and ensuring the security of grid.