安徽电气工程职业技术学院学报
安徽電氣工程職業技術學院學報
안휘전기공정직업기술학원학보
JOURNAL OF ANHUI ELECTRICAL ENGINEERING PROFESSIONAL TECHNIQUE COLLEGE
2012年
3期
46-50
,共5页
双回路%换位塔%跳线安装
雙迴路%換位塔%跳線安裝
쌍회로%환위탑%도선안장
double circuit%transposition tower%jumper installing
500kV双回路换位塔跳线安装工艺复杂,本文结合工程实际施工经验对其施工中的有关要点、难点进行总结研究。从施工前的准备工作,到组装跳线硬跳支撑杆、母线,提升硬支撑杆和跳串,安装各段跳线和间隔棒,液压耐张线夹等都进行了详细的说明。
500kV雙迴路換位塔跳線安裝工藝複雜,本文結閤工程實際施工經驗對其施工中的有關要點、難點進行總結研究。從施工前的準備工作,到組裝跳線硬跳支撐桿、母線,提升硬支撐桿和跳串,安裝各段跳線和間隔棒,液壓耐張線夾等都進行瞭詳細的說明。
500kV쌍회로환위탑도선안장공예복잡,본문결합공정실제시공경험대기시공중적유관요점、난점진행총결연구。종시공전적준비공작,도조장도선경도지탱간、모선,제승경지탱간화도천,안장각단도선화간격봉,액압내장선협등도진행료상세적설명。
500kV double circuit transposition tower jumper installing process is complicated. This paper combined with practical engineering experience, the relevant points and difficult points in the construction are summarized. From bar and bus, upgrading the pre-construction preparatory work, to assembling jumper hard jump support the hard support bar and hop string, installing jumpers and spacers, hydraulic pressuring strain clamp and so on are described in detail.