结合中电投江西公司景德镇电厂2×660MW超超临界机组现场调试过程中及机组转入正式商业运行后部分因DCS逻辑方面不完善而出现的问题和处理过程,根据本厂实际情况提出改进措施,对实施效果进行阐述,希望对同类机组的调试和生产具有一定的借鉴作用。
結閤中電投江西公司景德鎮電廠2×660MW超超臨界機組現場調試過程中及機組轉入正式商業運行後部分因DCS邏輯方麵不完善而齣現的問題和處理過程,根據本廠實際情況提齣改進措施,對實施效果進行闡述,希望對同類機組的調試和生產具有一定的藉鑒作用。
결합중전투강서공사경덕진전엄2×660MW초초림계궤조현장조시과정중급궤조전입정식상업운행후부분인DCS라집방면불완선이출현적문제화처리과정,근거본엄실제정황제출개진조시,대실시효과진행천술,희망대동류궤조적조시화생산구유일정적차감작용。
According to logic problems due to the imperfect in DCS and its processes during the on-site commissioning process and after into the formal commercial operation of the 2 × 660 MW supereritical generating units in Jingdezhen Power Plant of China Power Investment Corporation Jiangxi Branch, and also in accordance with the plant's actual situation, the improvement measures are advanced and its implement effects are elaborated, wanting to have some reference in the debugging and production of the similar units.