针对某火电厂改建基础工程中因受多项条件限制、常规方法不可行的问题,提出运用旋喷桩法并将底板连成整体的办法,实践证明采用本方法较好的解决了施工问题,对相关工程具有指导意义。
針對某火電廠改建基礎工程中因受多項條件限製、常規方法不可行的問題,提齣運用鏇噴樁法併將底闆連成整體的辦法,實踐證明採用本方法較好的解決瞭施工問題,對相關工程具有指導意義。
침대모화전엄개건기출공정중인수다항조건한제、상규방법불가행적문제,제출운용선분장법병장저판련성정체적판법,실천증명채용본방법교호적해결료시공문제,대상관공정구유지도의의。
In light of infeasibility of common methods used in the power plant reconstruction foundation engineering owing to various factors re- straint, the paper puts forward rotary churning pile method to connecting the bottom plate into the whole. Practice proves that the method better solves construction problems, which has certain guiding meaning for relevant engineering.