沿空留巷开采技术已在很多矿区得到广泛应用,在提高回采率、减少巷道掘进工程量的同时,却也加剧了采空区的漏风量。为了说明漏风给采空区防灭火工作造成的不利影响,强调堵漏在沿空留巷开采中应用的必要性,本文采用有限单元法对采空区速度场和氧浓度场进行了数值模拟,通过两者叠加划分出了自燃“三带”,并在数学模型的建立过程中考虑了遗煤氧化及采空区瓦斯涌出对氧气的稀释作用。计算结果表明:堵漏前自燃带最大宽度为196m,平均宽度为110m;堵漏后自燃带最大宽度为70m,平均宽度为63m。由此可见,漏风点的存在对采空区“三带”影响较大,且对采空区防灭火十分不利。所以沿空留巷开采中采取堵漏措施是十分必要的。
沿空留巷開採技術已在很多礦區得到廣汎應用,在提高迴採率、減少巷道掘進工程量的同時,卻也加劇瞭採空區的漏風量。為瞭說明漏風給採空區防滅火工作造成的不利影響,彊調堵漏在沿空留巷開採中應用的必要性,本文採用有限單元法對採空區速度場和氧濃度場進行瞭數值模擬,通過兩者疊加劃分齣瞭自燃“三帶”,併在數學模型的建立過程中攷慮瞭遺煤氧化及採空區瓦斯湧齣對氧氣的稀釋作用。計算結果錶明:堵漏前自燃帶最大寬度為196m,平均寬度為110m;堵漏後自燃帶最大寬度為70m,平均寬度為63m。由此可見,漏風點的存在對採空區“三帶”影響較大,且對採空區防滅火十分不利。所以沿空留巷開採中採取堵漏措施是十分必要的。
연공류항개채기술이재흔다광구득도엄범응용,재제고회채솔、감소항도굴진공정량적동시,각야가극료채공구적루풍량。위료설명루풍급채공구방멸화공작조성적불리영향,강조도루재연공류항개채중응용적필요성,본문채용유한단원법대채공구속도장화양농도장진행료수치모의,통과량자첩가화분출료자연“삼대”,병재수학모형적건립과정중고필료유매양화급채공구와사용출대양기적희석작용。계산결과표명:도루전자연대최대관도위196m,평균관도위110m;도루후자연대최대관도위70m,평균관도위63m。유차가견,루풍점적존재대채공구“삼대”영향교대,차대채공구방멸화십분불리。소이연공류항개채중채취도루조시시십분필요적。
It is popular to apply the plugging technology in mining of gob-side entry retaining. It can improve the recovery rate and reduce the tunnel heading amount. At the same time, it can also aggravate the air leakage of goaf. In order to explain the dangerous of air leakages and the necessary of plugging, the finite element method is applied to compute the distributions of seepage velocity field and oxygen concentration in this paper. The " three zones" distribution of spontaneous combustion is respectively divided by using the superposition of the fields of seepage velocity and oxygen concentration. And the effect of coal oxidization and gas emission were considered in mathematical model. The computed results show that the maximum width is 196m, the average width is ll0m of spontaneous combustion zone before plugging, the values respectively turn to 70m and 63m after plugging. Therefore, the existence of leakages have great effect no the "three zones" distribution of spontaneous combustion, and it is very unfavorable to mine fire control. It is so necessary to apply the plugging measures in mining of gob-side entry retaining.