箱梁%支架法%张拉%预拱度
箱樑%支架法%張拉%預拱度
상량%지가법%장랍%예공도
box girder%support method%tension%camber
结合工程实例,通过对现浇简支箱梁支架方案的分析比较,利用现浇支架法对900 t预应力简支箱梁进行了施工,从地基处理、支架搭设及预压、箱梁施工及预应力张拉等方面进行了论述,为类似工程施工积累了经验。
結閤工程實例,通過對現澆簡支箱樑支架方案的分析比較,利用現澆支架法對900 t預應力簡支箱樑進行瞭施工,從地基處理、支架搭設及預壓、箱樑施工及預應力張拉等方麵進行瞭論述,為類似工程施工積纍瞭經驗。
결합공정실례,통과대현요간지상량지가방안적분석비교,이용현요지가법대900 t예응력간지상량진행료시공,종지기처리、지가탑설급예압、상량시공급예응력장랍등방면진행료논술,위유사공정시공적루료경험。
Combining with the engineering examples,the paper adopts the cast-in-place support method to construct the 900 t prestressed simply-supported box girder by analyzing and comparing the cast-in-site simply-supported box girder support scheme,and indicates from the foundation treatment,the support erection and prestress,the construction of box girder,and the prestressed tension,so as to accumulate experience for similar projects.