冬期%铺架施工%技术方案
鼕期%鋪架施工%技術方案
동기%포가시공%기술방안
winter%laying construction%technical scheme
根据铺架施工工序,确保右线铺架稳步推进,优先抢抓湿接缝施工进度,桥梁支座锚固施工同步实施,分段组织左线铺轨,保障道砟日卸车作业量,有序安排大型养路机械作业,全面启动钢轨焊接、应力放散和锁定焊施工。
根據鋪架施工工序,確保右線鋪架穩步推進,優先搶抓濕接縫施工進度,橋樑支座錨固施工同步實施,分段組織左線鋪軌,保障道砟日卸車作業量,有序安排大型養路機械作業,全麵啟動鋼軌銲接、應力放散和鎖定銲施工。
근거포가시공공서,학보우선포가은보추진,우선창조습접봉시공진도,교량지좌묘고시공동보실시,분단조직좌선포궤,보장도사일사차작업량,유서안배대형양로궤계작업,전면계동강궤한접、응력방산화쇄정한시공。
According to the laying construction procedure, it needs to ensure the right line laying steadily, first to grab the wet joint construction schedule, make the synchronous imple-mentation of anchoring bridge supports construction, segmen-ted organize left line laying bal ast, security the day unloading work of railway bal ast, orderly arrangement the large mainte-nance machinery operation, ful swing rail welding, stress rel-ease and locking welding construction.