水电与新能源
水電與新能源
수전여신능원
HYDROPOWER AND NEW ENERGY
2014年
5期
49-50
,共2页
水电站%低压气机%润滑油%乳化
水電站%低壓氣機%潤滑油%乳化
수전참%저압기궤%윤활유%유화
hydropower stations%low pressure compressor%lubricant oil%emulsification
印尼阿萨汉一级水电站2台CompAir L15型低压气机在投产后4个月内连续发生2次润滑油乳化。通过认真分析,采用了提高气机运行温度和延长气机负载运行时间的措施,消除了此故障现象,改进后的运行实践证明所采用的措施是有效的。
印尼阿薩漢一級水電站2檯CompAir L15型低壓氣機在投產後4箇月內連續髮生2次潤滑油乳化。通過認真分析,採用瞭提高氣機運行溫度和延長氣機負載運行時間的措施,消除瞭此故障現象,改進後的運行實踐證明所採用的措施是有效的。
인니아살한일급수전참2태CompAir L15형저압기궤재투산후4개월내련속발생2차윤활유유화。통과인진분석,채용료제고기궤운행온도화연장기궤부재운행시간적조시,소제료차고장현상,개진후적운행실천증명소채용적조시시유효적。
In four months after the operation of CompAir L 15 low pressure compressors in Asahan I hydropower station in Indonesia , emulsification of lubricant oil occurred twice unexpectedly .Through a careful analysis , this problem was solved by increasing the operating temperature and extending the load time of compressors .Practice shows that the im-provement is effective .