2014年
6期
14-17
,共4页
操作%移动%组装%作业平台%射水沉桩%黄河
操作%移動%組裝%作業平檯%射水沉樁%黃河
조작%이동%조장%작업평태%사수침장%황하
operatinf%movinf%assemblinf%work platform%pile sinkinf by water Jettinf%Yellow River
对射水沉桩水上作业平台的技术指标、操作任务进行了介绍,平台的组装位置宜位于沉桩施工位置上游侧200 m范围内,组装时近岸浮体首先入水锚固,其他5块浮体依次入水锚固,组装方向线与滩岸线成10°~15°夹角;作业平台的水面移动是在平台下游驳船顶推缓慢下滑、上游逐步松放岸锚及河锚钢丝绳的共同配合下实现的,最终工作侧船舷与工程位置中心线距离应控制在0.6~0.7 m;作业期需在工作侧下游增加“八”字形锚固措施,确保各种复杂工况下平台锚固的安全稳定,平台顺工程位置线移动的动力主要是水流的冲击力和卷扬机的拉力,下滑速度控制及姿态调整主要依靠调整作业平台角部的缆绳实现。
對射水沉樁水上作業平檯的技術指標、操作任務進行瞭介紹,平檯的組裝位置宜位于沉樁施工位置上遊側200 m範圍內,組裝時近岸浮體首先入水錨固,其他5塊浮體依次入水錨固,組裝方嚮線與灘岸線成10°~15°夾角;作業平檯的水麵移動是在平檯下遊駁船頂推緩慢下滑、上遊逐步鬆放岸錨及河錨鋼絲繩的共同配閤下實現的,最終工作側船舷與工程位置中心線距離應控製在0.6~0.7 m;作業期需在工作側下遊增加“八”字形錨固措施,確保各種複雜工況下平檯錨固的安全穩定,平檯順工程位置線移動的動力主要是水流的遲擊力和捲颺機的拉力,下滑速度控製及姿態調整主要依靠調整作業平檯角部的纜繩實現。
대사수침장수상작업평태적기술지표、조작임무진행료개소,평태적조장위치의위우침장시공위치상유측200 m범위내,조장시근안부체수선입수묘고,기타5괴부체의차입수묘고,조장방향선여탄안선성10°~15°협각;작업평태적수면이동시재평태하유박선정추완만하활、상유축보송방안묘급하묘강사승적공동배합하실현적,최종공작측선현여공정위치중심선거리응공제재0.6~0.7 m;작업기수재공작측하유증가“팔”자형묘고조시,학보각충복잡공황하평태묘고적안전은정,평태순공정위치선이동적동력주요시수류적충격력화권양궤적랍력,하활속도공제급자태조정주요의고조정작업평태각부적람승실현。
It introduced the technical index and operation task of on-water work platform in pile sinkinf by water Jettinf. The assemblinf site of the platform was situated in the scope of 200 m of the upper reaches of pile sinkinf construction site. Near-shore floatinf body should be the first to be moved in water and anchored,then other 5 floatinf bodies were moved into water in turn and anchored. Assemblinf directional line and water front form an anfle of 10°~15°;on-water movinf of work platform was throufh pushinf by barfe lyinf in the lower reaches,looseninf the anchor on the shore in the upper reaches and the wire rope fasteninf on the anchor in the river. The distance between the work ship board and enfineerinf location center should be 0. 6~0. 7 m;anchorinf measure with splayed-shape pattern should be taken in operatinf period in workinf site to ensure the safety and stability of platform under complicated workinf conditions. The power of the platform movinf alonf enfineerinf position line was mainly the im-pact force of water stream and tension of windinf enfine. Slidinf speed control and position adJustment mainly relied on adJustinf the moorinf rope in the corner of work platform. Besides,announcements of on-water workinf were showed clearly.