天津港%高桩码头%板梁桥%接岸结构%方案比选
天津港%高樁碼頭%闆樑橋%接岸結構%方案比選
천진항%고장마두%판량교%접안결구%방안비선
Tianjin Port%piled wharf%plate-girder-bridge%shore approaching structure%option comparison and selection
由于受港区岸线规划等条件的限制,天津港某高桩码头的前沿线距后方吹填围埝仅50.0 m左右。在码头承台后方接岸结构的设计中综合考虑工程投资、工期和施工条件等方面的因素,经多方案比选最终选用板梁桥方案有效压缩了接岸结构宽度。该方案既能满足规划要求,又方便施工和后期使用,在节省投资和确保工期方面效果明显。
由于受港區岸線規劃等條件的限製,天津港某高樁碼頭的前沿線距後方吹填圍埝僅50.0 m左右。在碼頭承檯後方接岸結構的設計中綜閤攷慮工程投資、工期和施工條件等方麵的因素,經多方案比選最終選用闆樑橋方案有效壓縮瞭接岸結構寬度。該方案既能滿足規劃要求,又方便施工和後期使用,在節省投資和確保工期方麵效果明顯。
유우수항구안선규화등조건적한제,천진항모고장마두적전연선거후방취전위념부50.0 m좌우。재마두승태후방접안결구적설계중종합고필공정투자、공기화시공조건등방면적인소,경다방안비선최종선용판량교방안유효압축료접안결구관도。해방안기능만족규화요구,우방편시공화후기사용,재절성투자화학보공기방면효과명현。
Being restricted by harbor's shoreline layout, the front line of one piled wharf is only 500m far from rear cofferdam in Tianjin Port. Project investment, construction period and conditions are fully considered in the design of shore approaching structure, which is located in the rear of the wharf's platform. By comparing different options, plate-girder-bridge is eventually selected, which effectively reduces the width of shore approaching structure. The option not only satisfies the demand of harbor's layout, but also facilitates the construction and regular use. In addition, it guarantees the construction period and saves the investment.