以江门隧道施工为例,介绍了旋喷桩、搅拌桩等技术在浅埋富水软弱围岩暗挖隧道施工中的应用,分别阐述了多种技术的具体处理方案及相关技术要求,可供设计与施工参考。
以江門隧道施工為例,介紹瞭鏇噴樁、攪拌樁等技術在淺埋富水軟弱圍巖暗挖隧道施工中的應用,分彆闡述瞭多種技術的具體處理方案及相關技術要求,可供設計與施工參攷。
이강문수도시공위례,개소료선분장、교반장등기술재천매부수연약위암암알수도시공중적응용,분별천술료다충기술적구체처리방안급상관기술요구,가공설계여시공삼고。
Taking the construction at Jiangmen tunnel as the example, the paper introduces the application of some technologies, such as the chemical churning pile and the mixing pile and others, in the shallow, rich water, weak surrounding rock subsurface tunnel construction, and il- lustrates the factual treatment schemes for many technologies and their respective technical requirements, so as to provide some reference for the design and the construction.