断层%高压旋喷%泥石流固结
斷層%高壓鏇噴%泥石流固結
단층%고압선분%니석류고결
fault%high-pressure jet grouting%consolidation of debris
通过对中铝段村铝土矿7号进风井420中段过F4断层施工,总结了高压旋喷固结泥石流的施工经验,并详细介绍了其施工工艺及技术要点,以供其他同类地质条件巷道施工参考。
通過對中鋁段村鋁土礦7號進風井420中段過F4斷層施工,總結瞭高壓鏇噴固結泥石流的施工經驗,併詳細介紹瞭其施工工藝及技術要點,以供其他同類地質條件巷道施工參攷。
통과대중려단촌려토광7호진풍정420중단과F4단층시공,총결료고압선분고결니석류적시공경험,병상세개소료기시공공예급기술요점,이공기타동류지질조건항도시공삼고。
According to F4 fault construction at 420 middle section of No. 7 intake shaft in bauxite of Zhonglvduan Village, the paper sums up the construction experience for the debris flow of high-pressure solidified material of jet grouting, and mainly introduces its construction craft and technical points, so as to provide the construction reference for roadways with similar geological conditions.