电网规划%间歇性电源%高渗透率%安全性评估%连锁反应%复杂系统
電網規劃%間歇性電源%高滲透率%安全性評估%連鎖反應%複雜繫統
전망규화%간헐성전원%고삼투솔%안전성평고%련쇄반응%복잡계통
power grid planning%variable generation%high penetration%security assessment%cascading events%complex system
讨论了电力系统稳定性与安全性的从属关系,指出电网静态安全约束、暂态稳定约束和全过程安全评估宜分别在电网规划的不同步骤中考虑,提出了间歇性电源高渗透电网规划方案安全性评估流程。指出电力系统连锁反应事件部分过程具有开放的复杂巨系统的一些特性,其中一部分过程在仿真中难以准确模拟,需进行简化处理,而另一部分过程的前后事件之间具有强因果关系,这部分过程可采用改进的仿真软件进行模拟。提出了计及故障前发电系统状态的电网全过程风险评估计算方法,使用该方法,可将稳定设施费用和停电风险损失计入电网规划方案的综合年费用中,对方案进行安全性和经济性综合比较选择。
討論瞭電力繫統穩定性與安全性的從屬關繫,指齣電網靜態安全約束、暫態穩定約束和全過程安全評估宜分彆在電網規劃的不同步驟中攷慮,提齣瞭間歇性電源高滲透電網規劃方案安全性評估流程。指齣電力繫統連鎖反應事件部分過程具有開放的複雜巨繫統的一些特性,其中一部分過程在倣真中難以準確模擬,需進行簡化處理,而另一部分過程的前後事件之間具有彊因果關繫,這部分過程可採用改進的倣真軟件進行模擬。提齣瞭計及故障前髮電繫統狀態的電網全過程風險評估計算方法,使用該方法,可將穩定設施費用和停電風險損失計入電網規劃方案的綜閤年費用中,對方案進行安全性和經濟性綜閤比較選擇。
토론료전력계통은정성여안전성적종속관계,지출전망정태안전약속、잠태은정약속화전과정안전평고의분별재전망규화적불동보취중고필,제출료간헐성전원고삼투전망규화방안안전성평고류정。지출전력계통련쇄반응사건부분과정구유개방적복잡거계통적일사특성,기중일부분과정재방진중난이준학모의,수진행간화처리,이령일부분과정적전후사건지간구유강인과관계,저부분과정가채용개진적방진연건진행모의。제출료계급고장전발전계통상태적전망전과정풍험평고계산방법,사용해방법,가장은정설시비용화정전풍험손실계입전망규화방안적종합년비용중,대방안진행안전성화경제성종합비교선택。
Following a discussion of the affiliation of stability and security, it is pointed out that the static security constraints, transient stability constraints and whole process security assessment should be dealt with under different procedures in power grid planning. The procedure of security assessment for power grid planning under high penetration of variable generation is presented. It is pointed out that part of the courses of the cascading events is typical of the open complex giant system and should be simplified since it cannot be exactly simulated. The other part of the courses is with strong cause and effect relationship between the preceding and succeeding events and can be simulated by improved simulation software. By taking into account the pre-fault states of the generation system, the whole process risk assessing method is presented. With the method, the costs of stabilizing facilities and the power cut losses will be included in the composite annual costs for comparing and choosing the planning schemes. This work is supported by National High Technology Research and Development Program of China (863 Program) (No. 2011AA05A105).