石油钻采工艺
石油鑽採工藝
석유찬채공예
OIL DRILLING & PRODUCTION TECHNOLOGY
2014年
2期
126-128
,共3页
高成武%孙杰文%张强%王彦武%张剑峰
高成武%孫傑文%張彊%王彥武%張劍峰
고성무%손걸문%장강%왕언무%장검봉
气井测试%射孔%酸化%测试联作%三高气井%低压井测试%正压测试
氣井測試%射孔%痠化%測試聯作%三高氣井%低壓井測試%正壓測試
기정측시%사공%산화%측시련작%삼고기정%저압정측시%정압측시
Gas well testing%integrated perforation%acidizing and testing%high-temperature%high-pressure%and high-productivity gas well%low-pressure well testing%positive pressure test
针对阿姆河高温、高含硫复杂碳酸盐岩气藏A区低压井和B区高压井在作业过程中压井困难、井控风险高、储层二次伤害问题突出、资料录取困难等难题,开展了射孔、酸化、测试联作工艺研究。通过工具优选、工艺优化和现场试验,形成了两套适用于高温、高含硫和不同产量条件下的射孔、酸化、测试联作工艺,即适用于A区储层的低压井三联作工艺管柱(OMNI阀+LPR-N阀+RD阀)和适用于B区储层的高压井三联作工艺管柱(OMNI阀+RDS阀+RD阀)。该联作工艺在阿姆河复杂酸性气藏高、低压储层中共应用41口井,成功率100%,地质资料取全取准率100%,其中20余口井酸化后测试产量超过100×104 m3/d,单层射孔、酸化、测试作业时间平均缩短15 d以上,大幅度降低了作业成本、缩短作业周期的同时,大大降低了复杂碳酸盐岩气藏完井作业期间的井控风险,该研究为类似气藏的完井配套工艺提供了技术借鉴。
針對阿姆河高溫、高含硫複雜碳痠鹽巖氣藏A區低壓井和B區高壓井在作業過程中壓井睏難、井控風險高、儲層二次傷害問題突齣、資料錄取睏難等難題,開展瞭射孔、痠化、測試聯作工藝研究。通過工具優選、工藝優化和現場試驗,形成瞭兩套適用于高溫、高含硫和不同產量條件下的射孔、痠化、測試聯作工藝,即適用于A區儲層的低壓井三聯作工藝管柱(OMNI閥+LPR-N閥+RD閥)和適用于B區儲層的高壓井三聯作工藝管柱(OMNI閥+RDS閥+RD閥)。該聯作工藝在阿姆河複雜痠性氣藏高、低壓儲層中共應用41口井,成功率100%,地質資料取全取準率100%,其中20餘口井痠化後測試產量超過100×104 m3/d,單層射孔、痠化、測試作業時間平均縮短15 d以上,大幅度降低瞭作業成本、縮短作業週期的同時,大大降低瞭複雜碳痠鹽巖氣藏完井作業期間的井控風險,該研究為類似氣藏的完井配套工藝提供瞭技術藉鑒。
침대아모하고온、고함류복잡탄산염암기장A구저압정화B구고압정재작업과정중압정곤난、정공풍험고、저층이차상해문제돌출、자료록취곤난등난제,개전료사공、산화、측시련작공예연구。통과공구우선、공예우화화현장시험,형성료량투괄용우고온、고함류화불동산량조건하적사공、산화、측시련작공예,즉괄용우A구저층적저압정삼련작공예관주(OMNI벌+LPR-N벌+RD벌)화괄용우B구저층적고압정삼련작공예관주(OMNI벌+RDS벌+RD벌)。해련작공예재아모하복잡산성기장고、저압저층중공응용41구정,성공솔100%,지질자료취전취준솔100%,기중20여구정산화후측시산량초과100×104 m3/d,단층사공、산화、측시작업시간평균축단15 d이상,대폭도강저료작업성본、축단작업주기적동시,대대강저료복잡탄산염암기장완정작업기간적정공풍험,해연구위유사기장적완정배투공예제공료기술차감。
High-temperature, high-pressure and high-productivity gas wells in the Amu Darya gas ifeld encountered high well-control risks, dififculties in well killing, secondary pollution of reservoir formation, dififculties in acquisition of data and other challenges during testing operations. Researches have been carried out to improve testing technologies, and modify relevant tools. Through tool selection, process optimization and ifeld test, two sets of integrated perforaion, acidizing and testing processes for high temperature, high sulfur con-tent, and different productivities have been established, namely, OMNI valve+LPR-N valve+RD valve three in one string for low pressure wells in A block, and OMNI valve+RDS valve+RD valve three in one string for high pressure wells in B block. The new integrated process has been applied on 41 wells in the Amu Darya Gasifeld with a success rate of 100%, and a geologic data acquisition rate of 100%. Among these wells, over 20 had a production of over 100×104 m3/d after acidizing. Compared with conventional technologies, the integrated process can shorten the average perforation, acidizing, and testing time by over 15 days, lowering operation cost and well control risks during the completion of complex carbonate reservoirs substantially. The study provides references for the completion of similar gas reservoirs.