结合桃源村站-深云站区间的工程地质条件,介绍了超前小导管注浆支护加钢架施工配合三台阶开挖法的施工技术,并总结了施工中的注意事项,指出采用该技术解决了施工中的各种难题,取得了良好的施工效果。
結閤桃源村站-深雲站區間的工程地質條件,介紹瞭超前小導管註漿支護加鋼架施工配閤三檯階開挖法的施工技術,併總結瞭施工中的註意事項,指齣採用該技術解決瞭施工中的各種難題,取得瞭良好的施工效果。
결합도원촌참-심운참구간적공정지질조건,개소료초전소도관주장지호가강가시공배합삼태계개알법적시공기술,병총결료시공중적주의사항,지출채용해기술해결료시공중적각충난제,취득료량호적시공효과。
Combining with the engineering geological conditions of Taoyuan Village Station-Shenyun Station section,this paper introduced the construction technology of advanced small duct grouting support added steel frame construction with three step excavation method,and summa-rized the matters needing attention in construction,pointed out that using this technology solved all kinds of problems in construction,achieved good effect in construction.