工业工程与管理
工業工程與管理
공업공정여관리
INDUSTRIAL ENGINEERING AND MANAGEMENT
2014年
3期
109-115
,共7页
项目调度%现金流均衡%石大体育看台项目%优化模型%禁忌搜索
項目調度%現金流均衡%石大體育看檯項目%優化模型%禁忌搜索
항목조도%현금류균형%석대체육간태항목%우화모형%금기수색
project scheduling%cash flow balance%stadium of UPC%optimization model%tabu search
以一个具有代表性的实际工程项目---石大体育看台为对象,对现金流均衡项目调度优化问题进行了研究。首先介绍该工程项目的实际背景;随后基于承包商角度构建现金流均衡项目调度优化模型,并设计禁忌搜索算法进行求解,得到的满意进度与实际进度相比,现金流均衡幅度提升35.35%;最后,通过将理论结果与现实情况的对比分析,找出该工程项目在实际管理中存在的差距,研究了影响现金流均衡的关键因素,结论如下:通过提高支付比例、延迟截止日期、缩短支付时间间隔,可以减小现金流量缺口,实现现金流的有效均衡。研究可为项目进度管理、现金流控制提供定量化决策支持。
以一箇具有代錶性的實際工程項目---石大體育看檯為對象,對現金流均衡項目調度優化問題進行瞭研究。首先介紹該工程項目的實際揹景;隨後基于承包商角度構建現金流均衡項目調度優化模型,併設計禁忌搜索算法進行求解,得到的滿意進度與實際進度相比,現金流均衡幅度提升35.35%;最後,通過將理論結果與現實情況的對比分析,找齣該工程項目在實際管理中存在的差距,研究瞭影響現金流均衡的關鍵因素,結論如下:通過提高支付比例、延遲截止日期、縮短支付時間間隔,可以減小現金流量缺口,實現現金流的有效均衡。研究可為項目進度管理、現金流控製提供定量化決策支持。
이일개구유대표성적실제공정항목---석대체육간태위대상,대현금류균형항목조도우화문제진행료연구。수선개소해공정항목적실제배경;수후기우승포상각도구건현금류균형항목조도우화모형,병설계금기수색산법진행구해,득도적만의진도여실제진도상비,현금류균형폭도제승35.35%;최후,통과장이론결과여현실정황적대비분석,조출해공정항목재실제관리중존재적차거,연구료영향현금류균형적관건인소,결론여하:통과제고지부비례、연지절지일기、축단지부시간간격,가이감소현금류량결구,실현현금류적유효균형。연구가위항목진도관리、현금류공제제공정양화결책지지。
Taking a practical engineering project,the stadium of UPC,as background,this paper studied cash flow balanced project scheduling optimization problem.The project was presented at first.Then the optimization model was constructed from the contractor ’s perspective.Through solving the model using the tabu search algorithm,we obtained the desirable schedule which decreases the cash flow gap by 35.35%.Against the desirable schedule,the practical schedule was analyzed and the problems existing in the project management were found. The key factors influencing cash flow balance were studied as well and the conclusion was as follows:the contractor can strive for a larger payment proportion,a longer deadline,a shorter payment time interval to control the scale of cash flow gap,ensuring the cash flow to be balanced. The research in this paper can provide support for quantitative decisions on the management of schedule and the control of cash flows.