以某桩锚支护深基坑工程为例,通过对支护结构位移、周边建筑物沉降及锚索拉力等监测数据分析,探讨了各监测项的变化规律,监测结果表明各监测项累计最大值均未超过报警值,说明该基坑支护设计方案合理可行,可基本满足设计及施工要求。
以某樁錨支護深基坑工程為例,通過對支護結構位移、週邊建築物沉降及錨索拉力等鑑測數據分析,探討瞭各鑑測項的變化規律,鑑測結果錶明各鑑測項纍計最大值均未超過報警值,說明該基坑支護設計方案閤理可行,可基本滿足設計及施工要求。
이모장묘지호심기갱공정위례,통과대지호결구위이、주변건축물침강급묘색랍력등감측수거분석,탐토료각감측항적변화규률,감측결과표명각감측항루계최대치균미초과보경치,설명해기갱지호설계방안합리가행,가기본만족설계급시공요구。
Taking the deep foundation pit engineering of a pile anchor support as an example,through the monitoring data analysis on supporting structure displacement,surrounding buildings settlement,cable tension etc. ,discussed the variation laws of various monitoring items,the moni-toring results showed that the monitoring cumulative maximum values were more than the alarm values,explored the foundation pit supporting de-sign scheme was reasonable and feasible,could basically meet the design and construction requirements.