land development%earthwork excavation and ba-ckfilling amount%DEM
如何计算开发地块的土方挖填量是土地平整工程工作的重要环节。本文采用基于DEM 和TIN 数据生成的方法来模拟地形起伏情况,又在此基础上估算土地开发过程中的土方挖填量,并分析了与传统散点法计算土方挖填方量的优势。
如何計算開髮地塊的土方挖填量是土地平整工程工作的重要環節。本文採用基于DEM 和TIN 數據生成的方法來模擬地形起伏情況,又在此基礎上估算土地開髮過程中的土方挖填量,併分析瞭與傳統散點法計算土方挖填方量的優勢。
여하계산개발지괴적토방알전량시토지평정공정공작적중요배절。본문채용기우DEM 화TIN 수거생성적방법래모의지형기복정황,우재차기출상고산토지개발과정중적토방알전량,병분석료여전통산점법계산토방알전방량적우세。
How to calculate the excavation and fil volume of development plots is an important part of land leveling project work. This paper uses the method of DEM and TIN data generation to simulate the ups and downs of terrain, and based on it to estimate the excavation and fil ing amount in the process of land development, and analyzes its advantages with traditional scat er method to calculate the excavation and embankment volume.