本文介绍了某水电站厂房覆盖层的地质条件、本工程高喷施工的技术难点、主要工作设备、施工工艺和技术参数,分析讨论了灌浆中出现的问题并提出了解决问题的方案。高喷灌浆建造防渗墙在某水电站厂房围堰防渗中发挥了重要作用。
本文介紹瞭某水電站廠房覆蓋層的地質條件、本工程高噴施工的技術難點、主要工作設備、施工工藝和技術參數,分析討論瞭灌漿中齣現的問題併提齣瞭解決問題的方案。高噴灌漿建造防滲牆在某水電站廠房圍堰防滲中髮揮瞭重要作用。
본문개소료모수전참엄방복개층적지질조건、본공정고분시공적기술난점、주요공작설비、시공공예화기술삼수,분석토론료관장중출현적문제병제출료해결문제적방안。고분관장건조방삼장재모수전참엄방위언방삼중발휘료중요작용。
the article introduces the geological conditions of covering layer of the powerhouse of the hydropower station, the technical difficulties, the main work equipments, construction technology and technical parameters. and it also analyzes and discusses the grouting problems and proposed solutions to the problems. the impervious wall made of high pressure jet grouting plays an important role in cofferdam seepage prevention of the hydropower station.