CONSTRUCTION MANAGEMENT MODERNIZATION
2014年
4期
1-5
,共5页
张智慧%关军%张晓富%高勋
張智慧%關軍%張曉富%高勛
장지혜%관군%장효부%고훈
国际工程项目%合同付款条件%现金流%预付款条件
國際工程項目%閤同付款條件%現金流%預付款條件
국제공정항목%합동부관조건%현금류%예부관조건
international construction projects%contractor payment terms%cash flow%advance payment terms
合同付款条件对国际工程项目承包商财务具有重要影响。尽管承包商能够定性识别合同付款条件是否对本方有利,但并不能仅凭定性判断而获知其对资金压力和盈利水平的具体影响。为帮助承包商在合同谈判中能正确决策合同付款条件,在分析国际工程项目合同付款条件内容与性质的基础上,提出了定量分析合同付款条件对承包商现金流和财务影响的模型。以非洲某EPC道路工程为案例,假设了不同进度付款方式和预付款比例所构成的6种合同付款条件组合,分析了合同付款条件对现金流入、现金支出、垫资成本和盈利水平的影响,识别了不可接受的合同付款条件,为承包商正确决策提供了支持。
閤同付款條件對國際工程項目承包商財務具有重要影響。儘管承包商能夠定性識彆閤同付款條件是否對本方有利,但併不能僅憑定性判斷而穫知其對資金壓力和盈利水平的具體影響。為幫助承包商在閤同談判中能正確決策閤同付款條件,在分析國際工程項目閤同付款條件內容與性質的基礎上,提齣瞭定量分析閤同付款條件對承包商現金流和財務影響的模型。以非洲某EPC道路工程為案例,假設瞭不同進度付款方式和預付款比例所構成的6種閤同付款條件組閤,分析瞭閤同付款條件對現金流入、現金支齣、墊資成本和盈利水平的影響,識彆瞭不可接受的閤同付款條件,為承包商正確決策提供瞭支持。
합동부관조건대국제공정항목승포상재무구유중요영향。진관승포상능구정성식별합동부관조건시부대본방유리,단병불능부빙정성판단이획지기대자금압력화영이수평적구체영향。위방조승포상재합동담판중능정학결책합동부관조건,재분석국제공정항목합동부관조건내용여성질적기출상,제출료정량분석합동부관조건대승포상현금류화재무영향적모형。이비주모EPC도로공정위안례,가설료불동진도부관방식화예부관비례소구성적6충합동부관조건조합,분석료합동부관조건대현금류입、현금지출、점자성본화영이수평적영향,식별료불가접수적합동부관조건,위승포상정학결책제공료지지。
Payment terms have impacts on the contractor’s financial condition of international construction projects. Although contractors can qualitatively identify whether a given payment term is advantageous to gain profit,they do not have enough knowledge about the quantitative effects on financial pressure and profit only through qualitative judgment,thus affecting their decision-making. In order to help the contractors reasonably make decision in the process of negotiation on payment terms,a quantitative analyzing model of impacts of payment terms on cash flow and the contractor’s financial condition was built. taking a road engineering EPC project in Africa as an example,six advance payment terms combination from different progress payment ways and advance payment proportion were assumed,and the quantitative impacts of each payment conditions combination on cash inflow,cash outflow,the cost of contracting with fund,and profit were analyzed.Then the unacceptable contract payment conditions were identified,which could support the decision-making of contractors in the process of negotiation on payment terms.