针对焦炭塔裙座过渡段的结构特点,制定了详细的制造工艺,合理安排炼钢、锻造、机加工、焊接、热处理、无损检测等工序的顺序,并制定了各个工序的工艺措施,最后过渡段制造成功。结果表明,制定的过渡段制造工艺是合理的。
針對焦炭塔裙座過渡段的結構特點,製定瞭詳細的製造工藝,閤理安排煉鋼、鍛造、機加工、銲接、熱處理、無損檢測等工序的順序,併製定瞭各箇工序的工藝措施,最後過渡段製造成功。結果錶明,製定的過渡段製造工藝是閤理的。
침대초탄탑군좌과도단적결구특점,제정료상세적제조공예,합리안배련강、단조、궤가공、한접、열처리、무손검측등공서적순서,병제정료각개공서적공예조시,최후과도단제조성공。결과표명,제정적과도단제조공예시합리적。
According to the structural characteristics of coke drum skirt transition section making detailed manufacturing process, reasonably arranging the order of steelmaking forging, machining, welding, heat treatment and nondestructive testing and so on,formulation the process control measure in the each work process,the product was successfully manufactured at last.The results showed that it is reasonable for manufacturing process.