地震工程学报
地震工程學報
지진공정학보
China Earthquake Engineering Journal
2014年
3期
759-764
,共6页
于凯%左自波%王颖轶%黄醒春
于凱%左自波%王穎軼%黃醒春
우개%좌자파%왕영질%황성춘
沉管隧道%三维可视化%远程监测%GPS
沉管隧道%三維可視化%遠程鑑測%GPS
침관수도%삼유가시화%원정감측%GPS
immersed tube tunnel%three-dimension visualization%remote monitoring
沉管隧道管节的浮运、沉放及对接等是整个沉管隧道施工中的重中之重,这几个工序主要集中在水下进行,当前施工技术难以全面控制施工过程及其对接精度等,研究沉管隧道施工的可视化监测系统,对辅助现场精确测量、潜水作业以及指导安全管理施工具有重要的意义。针对沉管隧道施工工艺的特殊性,基于 VTK 的可视化和数据模型驱动等关键技术,采用并集成 GPS 测点坐标系统的构建与精确转换、PSM 配置,设计和开发了一种沉管隧道施工三维实时可视化远程监测系统,可以实时显示和查询施工过程中管节浮运、沉放的具体情况,实现沉管隧道实时可视化,并将该系统成功地应用于天津市海河沉管隧道工程的施工中。
沉管隧道管節的浮運、沉放及對接等是整箇沉管隧道施工中的重中之重,這幾箇工序主要集中在水下進行,噹前施工技術難以全麵控製施工過程及其對接精度等,研究沉管隧道施工的可視化鑑測繫統,對輔助現場精確測量、潛水作業以及指導安全管理施工具有重要的意義。針對沉管隧道施工工藝的特殊性,基于 VTK 的可視化和數據模型驅動等關鍵技術,採用併集成 GPS 測點坐標繫統的構建與精確轉換、PSM 配置,設計和開髮瞭一種沉管隧道施工三維實時可視化遠程鑑測繫統,可以實時顯示和查詢施工過程中管節浮運、沉放的具體情況,實現沉管隧道實時可視化,併將該繫統成功地應用于天津市海河沉管隧道工程的施工中。
침관수도관절적부운、침방급대접등시정개침관수도시공중적중중지중,저궤개공서주요집중재수하진행,당전시공기술난이전면공제시공과정급기대접정도등,연구침관수도시공적가시화감측계통,대보조현장정학측량、잠수작업이급지도안전관리시공구유중요적의의。침대침관수도시공공예적특수성,기우 VTK 적가시화화수거모형구동등관건기술,채용병집성 GPS 측점좌표계통적구건여정학전환、PSM 배치,설계화개발료일충침관수도시공삼유실시가시화원정감측계통,가이실시현시화사순시공과정중관절부운、침방적구체정황,실현침관수도실시가시화,병장해계통성공지응용우천진시해하침관수도공정적시공중。
In the process of immersed tube tunnel construction,floating and sinking are among the main priorities carried out underwater.The current construction technology cannot adequately or accurately control the floating and sinking processes,because the construction is carried out-un-derwater.The result of this is the work must be done by hand.The visualization system of im-mersed tube tunnel construction based on remote real-time monitoring is helpful in assisting with the measurements in construction sites and checking the results of diving operations for the dis-tance of abutting points.This makes this visualization system greatly significant and useful in maintaining the safety and management of the construction in the immersed tube tunnel.The con-struction is unique because of its floating and sinking processes.In this paper,a series of key tech-nologies are employed and integrated,including the establishment of the measuring point coordi-nate system making use of GPS and accurately converting coordinates,the use of the PSM config-uration,visualization technology based on VTK,Autodesk 3DS Studio MAX,model-driven data, Microsoft SQL Server Express,and others.A three-dimensional visualization system of immersed tube tunnel construction based on remote real-time monitoring is designed and developed by com-bining these key technologies.The system includes a GPS testing system in the pipe section and a dip angle system in the construction site for the processes of floating and sinking.The database of Microsoft SQL Server Express is included in the control center,along with the SOAP Web Service protocol communication.More specifically,the system can display the real-time situation of a sec-tion of pipe on the construction site,inquire about a great deal of information concerning the pipe section,and play back any time sequence of the construction process.The presented visualization system realizes the function of remote real-time monitoring for the tube’s floating and sinking, and it is successfully applied to the construction of the Haihe River immersed tube tunnel engi-neering in Tianjin.Its results closely match the information from the construction technical per-sonnel and can reflect the pipe section’s real-time situation and tendency in the toleration of the engineering error range.In addition,the system provides a guarantee for the safety and efficiency of the construction and can be further applied to related engineering projects.