TECHNIQUE OF SEEPAGE CONTROL
2014年
5期
154-157
,共4页
SMW工法桩%盾构井%围护结构%端头井加固%洞门处理%型钢拔除
SMW工法樁%盾構井%圍護結構%耑頭井加固%洞門處理%型鋼拔除
SMW공법장%순구정%위호결구%단두정가고%동문처리%형강발제
Soil Mixing Wall%shield well%enclosure structure%reinforcement of shield well%portal treatment%h-shaped steel pullout
采用SMW工法桩作为地铁车站盾构井围护结构的工程案例较少,类似工程的设计与施工缺少必要的工程经验作为借鉴。某地铁车站采用了SMW工法桩作为盾构井围护结构,施工过程中出现了洞门渗漏水的问题,结合工程险情的处理,对SMW工法桩在盾构工作井围护结构中的应用进行了探讨,形成如下结论:在保证洞门安全稳定的基础上,SMW工法桩具有很好的经济性;设计中应细化型钢拔出和洞门处理措施,并结合承压水影响确定端头井加固深度;施工中应统筹型钢拔除与盾构机掘进时间,拔除型钢时应严格履行洞门破除的管理流程,确保盾构进出洞安全。
採用SMW工法樁作為地鐵車站盾構井圍護結構的工程案例較少,類似工程的設計與施工缺少必要的工程經驗作為藉鑒。某地鐵車站採用瞭SMW工法樁作為盾構井圍護結構,施工過程中齣現瞭洞門滲漏水的問題,結閤工程險情的處理,對SMW工法樁在盾構工作井圍護結構中的應用進行瞭探討,形成如下結論:在保證洞門安全穩定的基礎上,SMW工法樁具有很好的經濟性;設計中應細化型鋼拔齣和洞門處理措施,併結閤承壓水影響確定耑頭井加固深度;施工中應統籌型鋼拔除與盾構機掘進時間,拔除型鋼時應嚴格履行洞門破除的管理流程,確保盾構進齣洞安全。
채용SMW공법장작위지철차참순구정위호결구적공정안례교소,유사공정적설계여시공결소필요적공정경험작위차감。모지철차참채용료SMW공법장작위순구정위호결구,시공과정중출현료동문삼루수적문제,결합공정험정적처리,대SMW공법장재순구공작정위호결구중적응용진행료탐토,형성여하결론:재보증동문안전은정적기출상,SMW공법장구유흔호적경제성;설계중응세화형강발출화동문처리조시,병결합승압수영향학정단두정가고심도;시공중응통주형강발제여순구궤굴진시간,발제형강시응엄격리행동문파제적관리류정,학보순구진출동안전。
Soil Mixing Wall (SMW pile ) is seldomly used in the construction of enclosure structure for the shield well of subway stations ,so the design and construction of similar projects lack the necessary referential engineering experiences . Here ,SMW pile was used in the shield well pit of a subway station ,during the construction a portal water leakage ap-peared ,based on emergency handling ,the application of SMW pile in the shield well was discussed .Accordingly ,come to a conclusion that the SMW pile can ensure the portal stability with excellent economy on the budget .The pullout of h-shaped steel and the portal treatment should be refined in the design ,and reinforcement depth of shield well should be determined by considering the confined water .The h-shaped steel pullout should co-ordinate with shield tunneling con-struction ,and it must strictly comply with the management processes to ensure the safety of gettting in and out of the well .