论述了巴江口水电站的施工导流标准与导流方式方法,分析了施工导流设计的技术特点。结合地形条件、施工期通航、工程提前发挥效益、永久与临时建筑物结合等因素,对导流方案进行综合比选,并介绍了最优方案的设计成果。
論述瞭巴江口水電站的施工導流標準與導流方式方法,分析瞭施工導流設計的技術特點。結閤地形條件、施工期通航、工程提前髮揮效益、永久與臨時建築物結閤等因素,對導流方案進行綜閤比選,併介紹瞭最優方案的設計成果。
논술료파강구수전참적시공도류표준여도류방식방법,분석료시공도류설계적기술특점。결합지형조건、시공기통항、공정제전발휘효익、영구여림시건축물결합등인소,대도류방안진행종합비선,병개소료최우방안적설계성과。
With regard to construction diversion of Bajiangkou Hydropower Project, the authors analyzed the river diversion standard and method as well as the technical characteristics of construction diversion design. Comprehen-sive comparison of diversion schemes was conducted in respects of topographical conditions, construction-period navigation, benefits, combination between permanent and temporary structures. An introduction was made on the de-sign of the optimum scheme.