为满足施工组织要求,通过对异型沉箱的浮游稳定计算、隔墙配筋计算及模型试验,确定沉箱拖运压舱物。使用手扳葫芦控位和钢架微调的组合替代起重船安装异型沉箱的工艺优化,提高了异型沉箱的安装效率,大幅度降低了施工成本。
為滿足施工組織要求,通過對異型沉箱的浮遊穩定計算、隔牆配觔計算及模型試驗,確定沉箱拖運壓艙物。使用手扳葫蘆控位和鋼架微調的組閤替代起重船安裝異型沉箱的工藝優化,提高瞭異型沉箱的安裝效率,大幅度降低瞭施工成本。
위만족시공조직요구,통과대이형침상적부유은정계산、격장배근계산급모형시험,학정침상타운압창물。사용수반호호공위화강가미조적조합체대기중선안장이형침상적공예우화,제고료이형침상적안장효솔,대폭도강저료시공성본。
In order to meet the construction requirements, we determined the hauling ballast of specially profiled caisson through the caisson floating stability calculation, wall reinforcement calculation and model test. We used a combination of man-ual hoist and fine steel to alternative the crane ship installation process of specially profiled caisson, which can improve the ins-tallation efficiency and reduce the construction cost.