针对某电厂拟新建的2台1000 MW空冷机组无取水定额问题,分析了电厂现有用水系统取水、排水状况,并对电厂一、二期机组各系统的节水工艺方案进行研究,提出了一、二期机组实施节水改造,将节约的新鲜水作为新建机组水源的用水方案。
針對某電廠擬新建的2檯1000 MW空冷機組無取水定額問題,分析瞭電廠現有用水繫統取水、排水狀況,併對電廠一、二期機組各繫統的節水工藝方案進行研究,提齣瞭一、二期機組實施節水改造,將節約的新鮮水作為新建機組水源的用水方案。
침대모전엄의신건적2태1000 MW공랭궤조무취수정액문제,분석료전엄현유용수계통취수、배수상황,병대전엄일、이기궤조각계통적절수공예방안진행연구,제출료일、이기궤조실시절수개조,장절약적신선수작위신건궤조수원적용수방안。
Based on no water catchment ration of 2 × 1000MW air cooled units newly constructed in a power plant ,the wa-ter supply and drainage status of the present water using system in this power plant is analyzed ,also the water saving pro-grams of the first and second stage of units in this power plant are researched and so the plan is raised that the saved fresh water is used as water source of the newly constructed units .